7.8.5 ELECTRICAL SUBSTATIONS
7.8.5.1 Transformer rooms
Transformer rooms are isolated from the other
electrical installations by partitioning walls so that the possibility of a
fire can be reduced substantially and its spread can be confined to the bare
minimum. Cable fire sealing and fire resistant coatings will be provided for
all H.T / L.T. and control cables, installed in transformer rooms, D.G. rooms,
battery rooms and the switchgear rooms.
7.8.5.2 D.G. rooms
The D.G. rooms
are partitioned and isolated from each other and from other electrical
installations for prevention & propagation of fires in the room.
Day tanks for
storage of diesel fuel are provided away from the D.G. sets in line with recommendations
of the Petroleum Act 1934.
7.8.5.3 Common Provisions
Since the ordinary cable joint are easily unwirable
and leads to frequent troubles, thermosetting type joints are only used in H.T. cables.
Trenches in which cable trays are laid are
walk through type facilitating quick and efficient servicing of cables. Motor
driven pumps are provided for removal of water form the water pits, if flooding
of trenches occurs any time.
7.9
FAILURE ANALYSIS FOR POWER SUPPLY SYSTEM
7.9.1 CABLING SYSTEM
Due to precautionary
design measures such as Fire barriers and fire stops and water sealing for all
outdoor to indoor cable pipe inserts, cabling system will be subjected to
minimum damage from fire hazard. Power, control and instrumentation cables will
be laid in separate trays and distinct route for different class of supply
cables will be followed to the extent possible.
7.9.2 LIGHTING SYSTEM
7.9.2.1
FAILURE OF CLASS IV SUPPLY
In the event of complete failure of class
IV supply, emergency lighting (which will
be 30% of the total lighting) fed from class III supply will be
operational subject to momentary interruption due to time taken by DG sets to
start (about 30 sec.). Critical lighting fed from class-II supply will remain
available.
7.9.2.2
FAILURE OF CLASS IV AND CLASS III SUPPLY
In the case of failure of class-IV and
class-III supply, Lighting fitting fed from class-II supply will be available
for safety exit and critical lighting.
7.9.2.3 FAILURE DUE TO SHORT CIRCUITS
AND EARTH LEAKAGE
The lighting feeder/ sub circuits will be
protected against short circuits by corresponding MCB and Fuse switch. Earth
leakage circuit breakers will be provided to protect the personnel from shock
hazards due to earth leakage.
7.9.3 PROCESS OFF-GAS (P.O.G) SYSTEM
There are two
nos. of motor control centre (MCC) panels i.e. MCC (group-A) and MCC (group-B),
one each for running and standby POG blowers. These two MCCs are physically
separate from each other. The incoming cable routings to these two MCCs are
physically segregated.
Case-I Power
interruption or maul-functioning in MCC (group-A).
The POG blowers
in this case shall be fed from MCC (group-B). The standby motors on MCC
(group-B) can be safely started and the corresponding POG blowers would run.
Case-II
Protection against fire.
In case of fire
in MCC (group-A), the standby motors on MCC (group-B) can be safely started and
the corresponding POG blowers would run. The fire will not affect MCC (group-B)
because this panel is physically separate from MCC (group-A).
7.10 POWER SYSTEM INTERLOCKS FOR AUTO MAINS
FAILURE (AMF)/ AUTO
CHANGE OVER
7.10.1 CLASS-IV SWITCHGEARS (33KV, 415V)
All the switchgears have been provided with suitable
metering devices for monitoring status and performances thereof. Some other
devices have been provided to protect the switchgear under abnormal conditions.
For 33 KV switchgear the incoming breakers and bus
section breakers are interlocked in such a way that it will not be possible to
close any incomer breaker and bus section breaker simultaneously. This is to
avoid parallel operation of the incoming breakers. Under normal operating
conditions the bus section breaker will be kept open and the power supply from
each incoming feeder will be confined to respective bus section. In the event
of failure/ outage of any incomer feeder, the entire load will be automatically
transferred to the healthy section by closure of the bus section breaker
contacts.
7.10.2 CLASS-III SWITCHGEAR (415 V)
DG set breakers and bus section breakers will be kept
open and power supply from each incomer will be confined to the respective bus
section. Provision exists for the selection of auto/ manual mode of starting
the DG set.
7.10.3 AUTO
SEQUENTIAL SWITCHING / EMERGENCY TRANSFER (EMTR) SCHEME FOR CLASS-III LOADS
During outages
of class-IV power supply on the incoming breaker of Class III
switchgear, the corresponding DG set
gets started automatically. The base loads on DG set are energized within 30
secs. at the instant of closure of DG breaker of Class III switch gear. The
motor loads shall be started in a pre determined sequence by a PLC based EMTR
panel. The following class-III motors shall be started in a pre determined
sequence-
Sr.
no.
|
System
|
Rating of motor (kW)
|
No(s). of motors
|
Type of starting
|
Running motors
|
Standby motors
|
Time delay (in secs.) provided for starting of single
motor
|
Instant of starting the motor
|
1.
|
E2 fan
|
90
|
5
|
VFD
|
3
|
2
|
5
|
0 sec.
|
2.
|
DOG1
|
11
|
2
|
VFD
|
1
|
1
|
5
|
15th.sec.
|
3.
|
DOG2
|
11
|
2
|
VFD
|
1
|
1
|
5
|
20th.sec.
|
4.
|
EOG
|
22.5
|
2
|
VFD
|
1
|
1
|
5
|
25th.sec.
|
5.
|
VOG
|
15
|
2
|
VFD
|
1
|
1
|
5
|
30th.sec.
|
6.
|
Negative Pressure System (NPS) Blower
-for lab glove boxes
|
2.25
|
2
|
DOL
|
1
|
1
|
5
|
35th.sec.
|
7.
|
Blister Off-gas (BOG) Blower -for
sampling block
|
3.75
|
2
|
DOL
|
1
|
1
|
5
|
40th.sec.
|
8.
|
Pump hot cell Blower (HCV)
|
1.5
|
2
|
DOL
|
1
|
1
|
5
|
45th.sec.
|
|
Total
no. of motors
|
|
21
|
|
|
|
|
|
|
Spares
|
|
25%
|
|
|
|
|
|
|
Grand
Total no. of motors
|
|
27
|
|
|
|
|
|
7.11 ELECTRICAL EQUIPMENTS
7.11.1 MOTORS :
Motors will be used for cranes, ventilation systems,
utilities, process pumps, etc. Motors shall conform to IS - 325, 3682 and
12615. All motors shall be squirrel cage energy efficient induction motors
having TEFC IP 55 enclosure with Class-F insulation and Class B temperature
rise conforming to IS 325 and 12615. Technical particulars of Motors are listed
in Table-XVII. Some of the major loads e.g. Supply fans, Exhaust fans and
Compressor motors shall be fed from VVVF (Variable Voltage Variable Frequency)
drives. The VVVF drives incorporate the features of energy efficiency and capacity
control. Technical particulars of VVVF drive are listed in Table-XVIII. The
typical technical specifications of motors shall be as follows :
(i) Motors shall be designed to deliver rated output
at rated power factor, continuously with
a)
Terminal
voltage variations from 415V by +/- 10%.
b)
Frequency
difference from 50 Hz by +/-5 %.
c)
Any
combination of a and b.
(ii) The temperature rise determined by resistance
measuring method shall not be more than 70 oC restricted to class B
temperature rise limit) over an ambient of 50 oC.
(iii) The class of insulation provided shall be class
F with the enclosure type TEFC IP 55.
(iv) The
tendered motors shall be
capable of starting and accelerating the driven equipment satisfactorily up to 80% of the rated speed within 10 - 15
seconds at a minimum voltage of 80% of the rated voltage at the motor
terminals. Any limitation in the loading pattern at this stage shall be clearly
indicated in the quotation. The motor
shall be designed for full-voltage Direct-on-line starting under normal course
of operation.
(v) Under
cold condition at room temperature, the
motors shall be capable of thr successive starts coupled to its driven
equipment with a time interval of one minute between each successive starting
operation and a fourth start 30 minutes later. The motor shall further be capable of three
equally time-spaced starts per hour under normal service conditions and the
motor shall withstand all stresses and give satisfactory performance.
(vi) Under hot condition, the motor shall be capable
of two starts coupled to its driven
equipment in quick succession (the time interval between each starting operation being less
than one minute) and a third start 20
minutes later. The motor shall further be capable of three equally time-spaced
starts per hour under normal service conditions and the motor shall withstand
all stresses and give satisfactory performance.
(vii) The motors
shall be capable of withstanding
for 15 sec, without stalling or abrupt change in speed (under gradual
increase of torque) an excess torque of 60% of their rated torque with the voltage and
frequency being maintained at their rated values.
(viii)
The starting torque and the pullout torque of the motor at rated voltage shall
be above about 250% of full-load torque.
(ix) Motors
shall be capable of satisfactory
operation at full loads for 10 minutes
without injurious heating at a motor terminal voltage of 80% of rated voltage.
(x) The safe stall time of the motor shall be above
the acceleration time of the driven equipment. Accelerating time of the motor
with rated load of driven equipment connected to it, shall not
exceed the corresponding safe
stall time of the motor even if stalling occurs when
motor is at
rated operating temperature (i.e.
under hot condition), at all applied voltages from 80% to 110% of rated
voltage.
(xi) The motors shall be capable of withstanding
without mechanical damage at least 120% of rated speed for 1 minute or as
imposed by the driven equipment, whichever is higher.
(xii) Motors shall be provided with cooling fan,
preferably made of ‘Cast Aluminium’.
(xiii) Terminal box shall be suitable for terminating
aluminium conductor FRLS insulated
armoured cables of appropriate size.
(xiv) Motor windings shall be given power house
treatment for protection against tropical weather conditions.
(xv) Motor vibration shall be limited as per IS 12065.
(xvi) The
permissible noise level shall be limited as per IS 12075.
(xvii) The motor efficiency and power factor shall be greater than 80% and 0.8 respectively.
(xviii) Motors
shall have anti-friction (ball roller or spherical roller type) bearings in
cartridge housings.
(xix) Routine and
type test as per IS-325 and IS-4029 shall be carried out. Additionally, the
following tests shall also be carried out.
a) Full load test to ascertain temperature
rise at 90% or 110% of rated voltage.
b) Enclosure protection
test.
c) Noise & vibration
measurement test.
d) Over speed test.
e) Speed-torque
characteristics.
f) Starting current Vs
time characteristics, at 80% & 100% voltages.
g) Rotor temperature
rise under locked-rotor condition.
h) Half-an-hour no-load
run test for all the motors.
(xx) The
motor winding as well as housing shall be given special epoxy-based anti-corrosive
treatment for protection against chemically aggressive gases or fumes. The
equipment shall be thoroughly degreased
& all rust, sharp edge and scales removed.
(xxi) Motors of 25kW and above shall be provided with
Positive Temperature Coefficient (PTC) thermisters for protection against high
winding temperature.
(xxii) Motors of
25 kW and above shall be provided with space heaters.
(xxiii) Motors
shall be rated for the load and duty cycle of the intended service.
(xxiv) Motors for certain applications viz. exhaust
fans, off-gas blowers shall be compatible for use with VVVF drives.
7.11.2 ILLUMINATIONPlant’s
lighting is envisaged with the energy efficient fluorescent lamps and/or
compact FL lamps for general areas and High bay fittings in areas with high
head room. 30% lighting on class-III power supply and exit lights with class-I
DC power supply shall be provided. 110V DC bulkhead type exit lights will be
provided on top of doors for evacuation under emergencies through all normal
and emergency exits of the plant. Illumination levels for various areas, rooms
have been chosen in line with IS recommendations/ BARC standards. The
illumination levels for various areas of the plant are attached vide Table-XVIV.
The salient features of lighting system are as
follows:
-Separate distribution panel shall be provided for
each floor.
-Lighting transformers shall be provided for high
block as well as sub-station and low block.
-Separate MCB DBs shall be provided for lighting
distribution of Class-IV, III, II & I loads.
-MCB distribution boards (DBs) shall be distributed in
the plant areas from functional usage point
of view and
from the point of view of building expansion joints.
-For lighting circuits, the load is restricted to a
maximum of 1 KW and for plug circuits it is restricted to 3 KW. A diversity of
50% is considered on plug circuits for sizing MCB DBs.
-Separate circuits for lighting and plug points.
-Separate conduits for class-IV, class-III, class-II
& class-I circuits.
-30% of the lights shall be provided with class-III
power supply.
-Class-II UPS and class-III lights shall be provided
in control room (50% each).
-DC bulkhead type exit lights shall be provided for
emergency evacuation.
-Inverter based class-I DC lights for service
corridors, access gallery areas for emergency evacuation purpose.
-High bay fittings shall be provided in areas with
high head room.
-Provision of back-up fluorescent lighting for areas
illuminated by high bay fixtures.
-Process cells to be equipped with ‘SON’ lights
through shielding plugs (withdrawable type).
-Gold plated 230V plug receptacles shall be provided
in cells for less maintenance.
-Separate neutral shall be provided in each circuit
for isolation.
-10 KA SPN MCBs shall be provided for lighting and
plug circuits.
-HFFR wires shall be used for building
electrification. 1.5 sq.mm. Cu wires for lighting circuits and 2.5 sq.mm. Cu wires for plug
circuits.
The following measures for energy conservation in
illumination system shall be adopted-
-Use of compact fluorescent lamps (CFLs) in cabins and
corridor areas.
-Use of low loss or electronic ballast.
-PID control for 50% normal lights in sampling gallery
and isolating corridor.
-Access/ Sampling gallery ‘normal’ lighting fixtures
controlled through occupancy based PID
sensors for energy conservation.
-LED lamps for ‘Aviation Obstruction Lighting
Fixtures’.
7.12 COMMUNICATION SYSTEM/
NETWORK
The plant’s communication network is a vital safety
related system. Apart from its usefulness in normal plant operations, it is
indispensable during emergency situations. A dedicated PA system shall be
provided for project ROP, AWTF and SFSF. Telephone exchange system shall be
common for both PREFRE and ROP.
The communication system wiring shall be provided for
the following sub-systems:
i)
Public Telephone cum Intercom system: This system shall be provided for
communication within and outside the plant complex. A dedicated 48V class-I
battery bank has been used for telephone
system.
ii) Public
address (PA) and emergency alarm system.
This
system shall be provided for giving alarms / paging to the plant staff during
normal and emergency condition. Class-II power supply is envisaged for public
address system.
7.13 Electrical Control System
Electrical control system of ROP covers “PLC
control system” and “Electrical SCADA
system”. “PLC control
system”
provides remote controls, interlocks and status monitoring of utility fans and blowers.
PLC system also
provides auto sequential starting of class-III
equipments at a pre-defined time intervals.
An
“Electrical SCADA system” is proposed for on-line monitoring, data logging and remote control of electrical equipments/
devices.
7.13.1 PLC
based control system
PLC based system is provided for remote control of
ventilation fans, off-gas blowers and interlocking of fans and blowers. The PLC panel also provides
auto sequential starting of class-III loads
during mains power outage. PLC panel has been provided with redundant CPU,
redundant power supply unit and redundant communication links. Control supply
to panel has been provided from class-II UPS system.
7.13.2 Electrical SCADA system
An Electrical SCADA
system is being provided to facilitate on-line monitoring and remote control of various electrical
equipments installed in the ROP plant from a PC based centralized control room.
Various analog and digital signals from Transformers, DG sets, Breakers, VFDs
(Variable Frequency Drives), UPS systems and Motors would be
gathered on a PLC through PROFIBUS/MODBUS cables. These devices have been provided with
communication features. Provision also exists for data display in Main Control
Room Panel (MCRP).
7.13.3 Control roomsAll the important motors have been provided
with remote control and annunciation facility. For all the motors local control
is available in the MCCs. Some of the motors of auxiliary systems such as
make-up area pumps, tank space pumps etc., have been provided with remote
annunciation, though their controls will be only local at the MCCs.
Local/remote selector switches for controlling the motors have been provided in
the main/ utility control-room so that the `start' facility is restricted to two
points only.
The control centre provided for the remote control and
annunciation of motors is :
a) Main control room in the Low Block of main process
building
b) Utility control room in high block building
7.13.4 Main control room
In this control room, there are 9 nos. of control
panels housing the actuators, controllers, recorders, monitors, indicators,
enunciators, measuring instruments and a seem graphic flow sheet. The panels are dedicated and identified process
wise.
The control and annunciation for the motors of the
process pumps installed in access galleries have been provided in the
respective process panel. A separate panel is dedicated to the electrical
systems where alarm annunciation of electrical drives have been provided for electrical
equipments.
List of electrical and utility equipments being
monitored/ controlled from main control room is listed vide Table-XVVII.
7.13.5 Control power supply
The instrument power distribution boards (IPDBs)
provide control power supplies to the following equipments in the main control
room.
24V DC power supply to transmitters, relays,
indicating lamps.
48V DC power supply to solenoid valves (SVs).
230V AC power supply to instruments, recorders,
annunciators, controllers, computers, data acquisition system, CCTVs, fire
alarm system etc.
The IPDBs to be located in the emergency control room,
shall be fed with class-II UPS power.
Critical instruments and health physics area monitors
have been provided with class-II uninterrupted power supply.
7.13.6 Annunciation Scheme
The alarm annunciator indicates the status of the
drive and gives alarm when the status changes, on operation of start/ stop push
button or on fault. The alarm
annunciation used is of two types. a) Integrated architecture type b) split
architecture type. They operate on 230 V AC power supply. One potential from NO/NC contact from the
drive's control circuit (either from
auxiliary relay or main contactor) is terminated on the anunciator’s signal
terminal for sensing the status of the drive.
Terminals are provided in the annunciator to connect the same to common
hooter for alarm. The annunciators are provided in 3x3x2, 4x3x2, and 4x4x2
configuration. The first two are of integral architecture and the last of split
architecture type.
The anunciator
logic followed is as under:
S.No. Sequence Audio alarm Visual indication
----------------------------------------------------------------------------------
1.
Normal condition
No Yes (ON window)
(Motor running)
2.
Change of status
Yes No (ON window)
(Motor tripped/stopped) Yes (OFF window)
3.
Acknowledgement
No No (ON window)
Yes (OFF window)
4.
Normal
No Yes (ON window)
(Motor started) No (OFF window)
--------------------------------------------------------------------------------
7.14 ELECTRICAL
SYSTEM INTERLOCKS
7.14.1 Power Systems
i) Safety interlocks and protection are provided for
transformers, DG sets, batteries, rectifiers, motors etc. as per standard
practices and IEEE recommendations.
ii) Earth leakage circuit breakers are provided as per
Indian Electricity Act.
iii) Earth fault annunciation will be introduced for
class-I DC batteries.
iv) Provision for manual initialization/ activation of
instrument/control supplies in control room
shall be made.
7.14.2 Process Pumps
Access Gallery Pumps
Provision for 3A and 2A cycle interlocks shall be made
at site.
Process Pumps Tank Space - (Acid Recovery
System/Formaldehyde Pumps)
Provision for high pressure/temperature/level cut-off
has been made in Motor control centres.
7.14.3 Interlocking Scheme For Supply Fans,
Exhaust Fans & Off Gas Blowers.There are 5 nos. of supply fan motors e.g.
V2F1, V2F2, V2F3, V2F4, V2F5. Each motor is of rating 3-phase, 415V, 75 KW. Fan
nos. V2F1, V2F3, V2F5 are fed from MCC(V1/V2)-GroupA and fan nos. V2F2, V2F4
are fed from MCC(V1/V2)-GroupB. All V2 fan motors are provided with Variable
frequency drives (VFDs).
1. There are 5 nos. of exhaust fan motors e.g.
E2F1, E2F2, E2F3, E2F4, E2F5. Each motor is of rating 3-phase, 415V, 90 KW. Fan
nos. E2F1, E2F3, E2F5 are fed from MCC(E2)-GroupA and fan nos. E2F2, E2F4 are
fed from MCC(E2)-GroupB. All E2 fan motors are provided with Variable frequency
drives (VFDs).
2. The interlock between V2 and E2 fan motors
shall be provided such that
Not more than any three nos. V2 fans
shall run at a time.
Not more than any three nos. E2 fans
shall run at a time.
If any running E2 fan trips,
corresponding one running V2 fan shall be tripped. Subsequently, one
standby E2 fan will come on-line
automatically in the event of failure of running E2 fan and one
standby V2 fan shall be switched ON
manually.
Once class-IV power supply to above
mentioned MCC panels goes off and class-III DG power
supply is restored to these MCC panels, pre-configured
one no. E2 fan shall start automatically.
In case of fire, all V2 fans are to be
switched off automatically and E2 fans shall remain ON.
3. DOG-1A, DOG-1B, EOG-1, VOG-1, ‘Negative
pressure system-1 (NPS-1)’, ‘Blister blower-1 (BB-1)’ & ‘HCV blower-1
(HCVS-1)’ motors are fed from MCC(POG)-GroupA. Likewise, DOG-2A, DOG-2B, EOG-2,
VOG-2, ‘Negative pressure system-2 (NPS-2)’, ‘Blister blower-2 (BB-2)’ &
‘HCV blower-2 (HCVS-2)’ motors are fed from MCC(POG)-GroupB. All DOG, EOG &
VOG blower motors are provided with Variable Frequency Drives (VFDs). All NPS,
BB & HCVS blower motors are provided with DOL starters.
The interlock between E2 fans and above blower
motors shall be provided such that If no E2 fans are
running, all Negative pressure system blower
motors (NPS-1 & 2 both), all ‘Blister Blower’ motors
(BB-1 & 2, both) and all HCV blower motors
(HCVS-1 & 2, both) shall be tripped.
6.
Interlocks between Off-gas blower motors shall be provided such that,
6.1
Out of 2 nos. of blowers i.e. DOG-1A and DOG-1B, only 1 no. of blower
shall run at a time.
6.2
Out of 2 nos. of blowers i.e. DOG-2A and DOG-2B, only 1 no. of blower
shall run at a time
6.3
Out of EOG-1 & EOG-2, only 1 no. blower shall run at a time.
6.4
Out of VOG-1 & VOG-2, only 1 no. blower shall run at a time.
6.5
Out of ‘NPS-1 & 2, only one no. blower shall run at a time.
6.6
Out of ‘BB-1 & 2’, only one no. blower shall run at a time
6.7
Out of ‘HCVS-1 & 2 blowers’, only one no. blower shall run at a
time.
6.8 In case of
failure/ stop of DOG-1A, DOG-1B shall start automatically and vice-versa.
6.9 In case of
failure/ stop of DOG-2A, DOG-2B shall start automatically and vice-versa
6.10 In case of failure/ stop of EOG-1, EOG-2 shall
start automatically and vice-versa.
6.11
In case of failure/ stop of VOG-1, VOG-2 shall start automatically and
vice-versa.
6.12
In case of failure/ stop of
‘NPS-1’, ‘NPS-2’ shall start automatically and vice versa.
6.13
In case of failure/ stop of ‘BB-1’, ‘BB-2’ shall start automatically and
vice versa.
6.14
In case of failure/ stop of ‘HCVS -1’, ‘HCV S-2’ shall start automatically
and vice versa.
7. In case any Off-Gas Blower (as mentioned in sr.
no.4 above) starts, corresponding one no. Digital Output (D.O.) signal shall be
generated by the PLC immediately for opening the suction valve and another Digital Output (D.O.) shall be
generated after a pre-set time delay for opening the discharge valve.
7.14.6 AHUs
Lab AHU motors shall be interlocked with the exhaust
fan motors (1R + 1S) of lab exhaust system in such a way that all AHU stop when
the running exhaust fan stops.
7.14.8 Underground Water Sump
Provision for cut off of U/G water pump motors is made
for water level high in O/H tank through a level switch. Provision for auto
start of motor also exists on fall of water level in O/H tank (a separate level
switch to be provided in O/H tank for the purpose).
7.14.9 Laboratories
Lab calciners are interlocked for high temperature
trips.
Compressors/Chilled Water
Compressors/Boilers
Safety
interlocks are provided with these system installations at site.
8.0 ACTION FOR COMPLIANCE
DURING CONSTRUCTION/ OPERATION :
8.1 ACTION FOR COMPLIANCE
DURING CONSTRUCTION :
8.1.1 A
gap of 5 metres should be maintained from 33 kV power line during construction.
There should
be
full electrical barrier. Vertical barriers should be installed with GI sheets
during construction of
new
sub-station.
8.1.2
The
MCC/ PCC panel shall be kept away from the corrosive atmosphere in order to
prevent corrosion.
8.2 ACTION FOR COMPLIANCE
DURING OPERATION :
8.2.1 Any
one 33 KV feeder is capable of meeting
entire load requirement of plant for normal
operation. Any 1 (one) out of the 2 (two) HT feeders shall
be available for plant operation.
8.2.2
Loading
of HT incomers from ROP sub-station shall be restricted to 300 Amps (maximum).
8.2.3
H.V.
circuit breaker earthing trucks shall be used for the earthing purpose during
shut down jobs.
8.2.4
If all
the two feeders fail, normal
power supply will not
be available in the plant. DG-
sets will provide emergency power
supply under such circumstances.
8.2.5
During
the healthy condition, three phase AC voltage
at MV switchgears shall be maintained between 415 to 433V by keeping the
off-load tap changer set at normal tap position. However, if the grid is
unhealthy for long period, the off-load tap changer shall
be set at suitable position to
maintain the transformer secondary
voltage on load, within 415V ± 5%, depending upon the grid conditions.
8.2.6
Transformer winding
temperature shall not exceed a limit of 155 °C. (as per winding resistance indicator) under normal
conditions.
8.2.7
Load currents,
voltage, power in KW, power factor, power consumption in KWH,
frequency shall be monitored in every shift
on all the H.T./ L.T. switchgears.
8.2.8
In
case of failure/outage of 110V DC control supply in ROP substation, a visual
indication and audio alarm shall be annunciated and the control supply shall be
made available for the breaker controls within
one hour. "Trip circuit healthy" indication shall be monitored
continuously.
8.2.9
At-least
one DG set shall be available for
plant-operation. If any DG Set fails/develops a fault/problem, it shall
be made available for operation within 7 days.
8.2.10 The diesel generator sets shall be started
and run on no-load or under partial-load
for 30 minutes every week, under manual
mode of controls. The D.G. set shall be tested on load once in a month under manual mode of control.
8.2.11 Automatic actuation of the diesel
generators shall be ascertained by simulating failure of normal
power supply and the gen-sets
shall be load tested for one hour at least once every month.
8.2.12 For evaluating the performance of the DG
set and to establish stabilized engine parameters, the DG set shall be tested
to its full load using water load bank(s).
This will ensure that steady state engine parameters like temperatures
are within design limits and also ensure rated capacity of DG set.
8.2.13 In order to ensure healthiness of engine
safety trips for DG sets, yearly calibration of engine mounted sensors like
cooling water temperature, lube oil pressure, lube oil temperature etc. shall
be carried out.The fuel oil level in the day tanks and air pressure in
compressed air cylinders shall be checked everyday to ensure full stock. Similarly, air pressure in compressed air
cylinders; cooling water temperature/ level and
lube oil pressure shall also be
checked every hour during D.G. operation for ensuring trouble free operation of D.G. sets.
8.2.14 In case of failure of ‘PLC based auto
sequential starting system’, the same shall be made available within 7-days.
Exhaust and off-gas fans shall have to be connected to the class-III power
supply one by one in a preset sequence with an interval of about 1 minute
between two subsequent motor-starters.
8.2.15 If any circuit breaker/switch fuse unit of
class-III switchgear develops a
fault it shall
be repaired/replaced with an identical spare unit within 24 hours. Power
supply to the concerned emergency load centres shall be restored within 1 hour
with the help of duplicate emergency feeder of provided
for the purpose.
8.2.16 If UPS-A of the two UPS sets (i.e. UPS-A
& UPS-B) becomes inoperable, UPS-B shall feed the loads of UPS-A. If UPS-B
out of two UPS sets becomes inoperable, the class-III bypass line of UPS-B
shall feed the loads of UPS-B. The inoperable UPS shall be made operable within
7 days. On the simultaneous failure of incoming power supply to both UPS, both
UPS will work on their respective battery for 1 hour and plant shall be shut down
in the planned manner.
8.2.17 To assess capacity of batteries in the UPS
system, capacity test on battery bank shall be carried out annually.
8.2.18 The
electrolyte level, specific gravity
(1.2) and voltage of pilot cells (2.2 volts) shall be measured
in every shift i.e. thrice a day and for all the cells once a week.
Batteries shall be load tested once in two years. Healthiness of D.C. supply and its
indications on all the switchgears shall be checked every day.
8.2.19 One ACVR constitutes ‘Float cum Boost’ and
‘Float charger’. During boost charging of a ‘discharged’ battery set, the
battery set shall be charged by the corresponding ‘Float cum
Boost charger’ and the other Float charger shall feed to the D.C. loads.
Main bus-coupler shall remain open.
8.2.20 DC exit lights connected to class-I power
supply system shall be tested once in three months. Record for the same shall
be maintained.
8.2.21 Battery discharge load test shall be
conducted for at least 10 hours.
8.2.22 Proper administrative control and approved
procedure shall be followed during crane operation, with class-III power
supply, to prevent breakdown.
8.2.23 Performance reliability of protection
relays, including settings shall be carried out yearly.
8.2.24 Insulation rubber mats shall be installed
before all the electrical panels.
8.2.25 Measurement of earth resistance shall be
carried out quarterly in a year.
8.2.26 Checking electrical healthiness of portable
tool shall be carried out as & when tools are issued. Records for the same
shall be maintained.
8.2.27 Master PM schedule shall be prepared for
the entire facility. Maintenance history cards for all the equipments shall be
prepared.
No comments:
Post a Comment