ELECTRICAL SYSTEM DBR
1.0 INTRODUCTION:
Project ROP (Revamping of Power
Reactor Fuel Reprocessing (PREFRE) plant) at Tarapur is a radio chemical
facility with a reprocessing capacity of 100 Te of spent fuel, which is aimed
to facilitate life extension and the capacity augmentation of the existing
PREFRE plant at Tarapur. Power Reactor Fuel Reprocessing (PREFRE) plant was
designed, built and commissioned in 1974, to re-process the spent fuels from
CIRUS, RAPS, NAPS and MAPS reactors. As the existing PREFRE plant is nearly
three decades old, its process systems and the auxiliary support systems like
effluent handling in tanks, the piping network, waste storage etc. are proposed
to be up-graded through the ROP Project. Also as some new atomic power stations
have been recently commissioned at Kakrapara, Kaiga and Kota, capacity
augmentation of PREFRE is planned through the ROP project within the PREFRE
complex.
Owing to the
nature of processes employed, which involve handling of highly radioactive
process solutions, efficient performance of the Electrical Power system is
critical to plant safety. Availability
of a reliable and adequate Mains power supply is very critical for safe
operation of the plant. Similarly the emergency power supply systems need a
high degree of reliability for plant safety and environment protection.
2.0 SCOPE OF THE DESIGN BASIS REPORT
This Design Basis Report
covers mainly design
criteria, system description, salient
features of
components electrical system
of ROP sub-station, criteria for selection of safety
and non-safety
related electrical equipments, postulated initiating events and their consequences
on safety related
systems to meet
their intended functions. Separate DBR has been prepared for ROP facility.
3.0 DESIGN
OBJECTIVES
3.1 Class-IV
Mains Power Supply System (33 KV)
33KV `Mains’ HT power system shall be designed to
provide 33 KV mains power to ROP, PREFRE and proposed UNCF.
3.2 Class-IV Mains Power Supply System (415 V)
415V `Mains’ LT power system shall be designed to meet
the needs of class-IV power supply of projects ROP, AWTF and SFSF.
3.3
Class-III
power for ROP, AWTF & SFSF
The system design
shall ensure availability of class-III power supplies for ROP, AWTF and SFSF
projects.
3.4
Class-II
Power Supply System (230 V)
The system shall
be designed to meet the needs of 230V, class-II power supplies (UPS) for
C&I loads of ROP project.
3.5
Class-I
DC Power Supply System (110 V)
The system shall
be designed to meet the needs of 110V, DC class-I power supplies for switchgear
controls and exit lights of ROP project.
3.6 To ensure safety of plant and the O&M
personnel
System design
shall ensure the safety of plant equipment and that of operating/ maintenance
personnel during normal as well as emergency conditions like power
outages, flooding and outbreak of fire.
3.7 To provide adequate illumination levels
The design shall
ensure adequate illumination levels in the plant areas for ease of operation
and maintenance.
3.8 To ensure Continuous availability of Power
Electrical design
facilitates periodic in-service inspections and preventive maintenance for
ensuring availability of power to the important plant systems.
3.9 To reduce man-rem expenditures.
The design shall
facilitate remote maintenance for the electrical equipments planned to be
installed in the radioactive areas, so
as to reduce man-rem expenditures.
3.10 To enhance
system safety
Enhancement of
system safety by using requisite quality materials/ equipments.
3.11 Provisions for Future Expansions
The system design
shall have provisions for expansion and up gradations in future.
4.0 DESIGN CRITERIA
The
ROP electrical system shall be designed to meet the following criteria :-
4.1 Load
requirements: HV systems
4.1.1 The entire 33KV ‘Mains’ HT power system shall be
designed for catering to a total power requirement of about 15 MVA at a fault
level of 1500 MVA to feed and provide electrical power to PREFRE, ROP and
proposed UNCF substations for normal Operation and Maintenance of these plants.
The 33 kV Mains incomers shall be capable of meeting this power requirement
independently.
4.2 Load
requirements: LV systems
4.2.1 The 415 Volt electrical system consisting of
Class IV power supply system, Class III power supply system, Class II power
supply system and Class I power supply system shall be capable of meeting the
class-IV power requirement of about 2455 kVA, class-III power requirement of
about 850 kVA, class-II power requirement of about 41 kVA and class-I power requirement
of about 25 kW or 350 A for half an hour.
4.3 References/
Guidelines
The compliance of following codes shall be ensured :
-Indian
Electricity Rules
-NEC-85
-AERB Codes
(SGD-11) & guides
-Latest
applicable IS & IEEE standards.
The detailed reference list is given in Annexure-1.
4.4 Classification
of power supplies
The following
power supply systems have been envisaged at ROP substation to meet
operational & safety requirements:
4.4.1 Class-IV power supply: Alternating current power supply to meet
plant’s O&M loads & the auxiliaries, which can tolerate prolonged
interruption without affecting safety of the plant, is classified as Class-IV
Power Supply. 415 Volt mains supply has been provided from ROP substation. Two
33KV under ground cable feeders have been brought to the ROP substation from
MSEB/NPCIL’s 220 KV switchyard to meet Class-IV power requirement of entire site.
33KV power supply is further stepped down to 415 Volt class IV power in
the indoor ROP substation, from where
415 V power is distributed to the ROP,
AWTF & SFSF facilities.
4.4.2 Class-III power supply: Alternating current power supply to safety
related systems, that can tolerate short interruptions (up to 2 minutes) is
classified as Class-III power supply. Under normal conditions, this power
supply is derived from Class-IV and in case of loss of Class-IV power supply,
standby DG sets are automatically started and connected to the Class-III
switchgear systems through AMF logic to meet emergency power requirements of
the plant. The diesel generators and the Class-III switchgear systems are
provided in the indoor ROP substation, from where 415 V CLASS III power is
distributed to the ROP, AWTF & SFSF facilities.
4.4.3 Class-II
power supply: Critical
control systems viz. Public Address System, criticality monitors, control
instruments etc. powered through UPS
shall be available continuously. UPS for class II power supply system are
provided at the ROP high block building.
4.4.4 Class-I power supply:
Direct current power supply to loads which require direct current power is
called Class-I power supply. Normally direct current power is derived through
an AC to DC rectifier connected to Class-III power supply. Battery back up is
provided so that direct current power supply continues to be available even
when Class-III power or rectifier fails. Class-I power supply shall be provided
in the ROP sub-station.
The break-up of individual
maximum demand of above mentioned power supply systems of ROP project is as
under:
HIGH BLOCK BUILDING
Class-IV Class-III Class-II Class-I
1000 KVA 495KVA 40KVA 10 KW
LOW BLOCK BUILDING
Class-IV Class-III Class-II Class-I
40 KVA 5 KVA 1 KVA (16 KW) 1 KW
SERVICE BUILDINGS
Class-IV Class-III Class-II Class-I
600 KVA 100KVA - 1 KW
The load list of
class-IV, class-III, class-II and class-I power systems of ROP project are given
in Table-II, Table-III,
Table-IV and Table-V
respectively.
4.5 Functional
requirements
4.5.1 The design shall ensure quality power for the
electrical drives and devices through two independent mains power
supply and by using safe, reliable, energy efficient
and easy to maintain type system components and the associated
distribution network.
4.5.2 The permissible steady state voltage and
frequency limits (in terms of maximum, minimum & percentage) for
continuous operation of equipments connected to
various voltage levels are indicated below:
System Voltage
|
Permissible values
|
System Frequency
|
Permissible values
|
||||
Maximum
|
Minimum
|
Range in %
|
Maximum
|
Minimum
|
Range in %
|
||
Class IV
& class III
|
|||||||
415 V(AC)
|
439.9 V
|
390.1 V
|
± 6 %
|
50Hz
|
51.5Hz
|
48.5Hz
|
± 3%
|
230V
AC
|
243.8 V
|
216.2 V
|
± 6 %
|
50Hz
|
51.5Hz
|
48.5Hz
|
± 3%
|
Class II
|
|||||||
230V AC
|
235.75V
|
224.25V
|
± 2.5%
|
50Hz
|
50.5 Hz
|
49.5 Hz
|
± 1%
|
Class I
|
|||||||
110V DC
|
112.75 V
|
97.25 V
|
± 2.5%
|
|
|
|
|
4.5.3 The permissible
transient state voltage
and frequency limits ( in terms of
maximum,
minimum & percentage) for
continuous operation of equipments connected to various voltage levels
are indicated below:
System Voltage
|
Expected Transient Voltage Variation
|
Expected Transient Frequency
Variation
|
||||
Magnitude
|
Percentage
|
Recovery
Time
|
Magnitude
|
Percentage
|
Recovery
Time
|
|
Class-IV
|
556 V
|
+34%
|
50 msec.
|
54.25Hz
|
+8.5%
|
15
sec. To
|
415 V AC
|
290.5
V
|
-30%
|
200 ms.
|
|
|
52.5 Hz
|
|
|
|
|
|
|
|
Class-III
|
556.1 V
|
+34%
|
50 msec.
|
54.25Hz
|
+8.5%
|
15 sec. to
|
415 V AC
|
498 V
|
+20%
|
2.4 sec
|
52.5Hz
|
+5%
|
52.5 Hz
|
|
332 V
|
-20%
|
2.4 sec.
|
47.5Hz
|
-5%
|
2.4 sec.
|
|
|
|
|
|
|
|
Class–II
|
253 V
|
+10%
|
50 msec.
|
51Hz
|
+2%
|
----
|
230 V AC
|
207 V
|
-10%
|
50
msec.
|
49Hz
|
-2%
|
----
|
Class–I
|
112.75 V
|
+2.5%
|
50 msec.
|
-
|
-
|
----
|
110 V AC
|
97.25 V
|
-2.5%
|
50
msec.
|
-
|
-
|
----
|

4.5.4 The short circuit fault level at various buses i.e. 33 KV, 415V
class-IV, 415V class-III, 240V class-II and 110 V DC class-I is indicated
below:
|
|
|
Required rating for SWGR.
|
Switchgear Rating
|
||
Sl. No.
|
System
|
Fault Level for the bus
|
Making level
|
Symmetrical
Interrupting Level/withstand capacity
|
Making level
|
Symmetrical
Interrupting Level/withstand capacity for 1 sec.
|
1.
|
33 KV AC
Class-IV system
|
17.5 KA (rms)
|
36.75 kA
|
17.5 KA (rms)
|
52.75 kA
|
25 KA (rms)
|
2.
|
415 Volt AC
Cl-III, Cl-II & Cl-IV with Cl-III to Cl-II tie CB closed
|
52.5KA (rms)
|
110.77 KA peak
|
52.5 KA (rms)
|
137KA peak
|
65 KA (rms)
|
|
|
|
Required
rating for SWGR.
|
Switchgear
Rating
|
||
Sl. No
|
System
|
Fault Level for the bus
|
Making level
|
Symmetrical Interrupting Level/withstand capacity
|
Making level
|
Symmetrical
Interrupting Level/withstand capacity for 1 sec.
|
3.
|
Power DC
battery
|
9.4 KA
|
----
|
9.4 KA
|
----
|
20 kA
|
The above
table indicates the interrupting ratings of switchgear provided at various
voltage level.
From this
data it can be seen that the ratings are adequate with adequate margins.
4.5.5 33 KV/433
Volt transformers are provided with off circuit tap links having ±5% range. The
table below gives the terminal voltage for various load conditions for constant
input voltage.
Sr.No.
|
Grid
Voltage
|
Load
as % of full load
|
Secondary
voltage at rated tap
|
Required
tap position
|
Expected
secondary voltage
|
1.
|
33 KV
|
|
|
|
|
1.1
|
|
0%
|
433 V
|
Rated tap
|
433 V
|
1.2
|
|
50%
|
415.6 V
|
Rated tap
|
415.6 V
|
1.3
|
|
100%
|
398.3 V
|
-2.5%
|
444V
|
2.
|
33 KV+12%
|
|
|
|
|
2.1
|
|
0%
|
484.96V
|
+5%
|
461.8V
|
2.2
|
|
50%
|
465.56V
|
+5%
|
443.3V
|
2.3
|
|
100%
|
446.16V
|
+5%
|
424.8V
|
3.
|
33 KV-9%
|
|
|
|
|
3.1
|
|
0%
|
394V
|
-5%
|
414.7V
|
3.2
|
|
50%
|
378V
|
-5%
|
398.1V
|
3.3
|
|
100%
|
362.5V
|
-5%
|
381.5V
|
From the above
table, it can be observed that steady state 433V bus voltage is maintained for
the expected voltage variation on 33 KV side and various load conditions.
4.5.6 The class-III power supply should automatically
come on stream when the class-IV power supply fails due to any reason. All the
essential base loads like lighting, health and safety instruments, plant
communication equipment etc., should be energized within time duration of 30
–100 seconds. Power supply for all other bulk loads like exhaust and off-gas
fans should be made available within a time span commensurate with the health
and safety requirement.
4.5.7 Rating of the two DG sets shall be so chosen
that the entire class-III loads of the plant can be continuously fed even if
one of the sets is not available.
4.5.8 Bulk-oil
storage facility for DG Room shall be common for ROP, PREFRE & IP-1, which
shall be suitably located between PREFRE and IP-1 and shall be about 15m away
from any adjacent structure. Day tanks for ROP DG sets are to be near ROP
substation adjacent to the furnace oil storage bldg.
4.5.9
In most of the plant areas, 30-40% of the lights installed shall be
provided with class-III power supply whereas in control room, 50% of the lights
installed shall be provided with class-III power supply & rest from
class-II. Some of the plant facilities shall have special lighting provisions
such as 250 W HPSV/ 500 W halogen lamp fixtures for fuel pond lighting,
150/250W high pressure sodium vapour lamps in the dissolver cell, 250 W HPSV
for process cells, 35W/55 W SOX/ 18 W CFL for Hot cell & Blister (cubicles)
lighting Flame proof fixtures with ML lamps for inflammable material stores. All
the distribution boards have been provided with a 25% diversity factor.
4.5.10 The instrument power distribution
board (IPDB) providing control power supplies to various instruments in control room,
shall be fed with two feeders of Class II power. Each feeder shall be capable
of meeting the entire instrumentation load. Duplication of feeders is to
enhance the reliability and availability of power supply for the
instrumentation system.
4.5.11 Class-I DC power supply to critical
control relays, instruments & sub-station auxiliary loads shall be fed
continuously through DC switchboard receiving power normally from the ACVRs and
backed up with storage batteries.
4.5.12 Battery banks shall be adequately
designed to supply the entire class-I power requirement for a period of 30
minutes at high discharge rates without affecting the life of batteries.
4.5.13 In the event of non availability of
Class IV or Class III power supply to ACVRs, or during failure of ACVRs, the
batteries take over the function of feeding DC power to plant's critical loads
like switch gear controls, indications, communication system and also to the DC
`EXIT’ lighting along the evacuation routes in active areas.
4.5.14 The system design should ensure the
safety of plant equipment and that of the operating /maintenance personnel not
only during normal operation but also during emergency conditions like outbreak
of fire.
4.5.15 The design should be such that all
important process loads can be controlled from the main control room. Indication
of the availability of power supplies and ON/OFF status of major loads should
also be available at the control room.
4.5.16 The layout of the power distribution
centers should be such as to avoid lengthy cabling so that voltage drops can be
minimized with consequent improved performance of plant equipment.
4.5.17 All major load centres should be
segregated from each other so that planned or non- planned power interruption
in one area does not affect the operation in other areas.
4.5.18 All electrical motors shall be
connected through DOL type starter but for E2 fan motors
which will have VVVF drives.
4.5.19 Design shall facilitate control of
all important process loads from main control room.
4.6 Safety
requirements
4.6.1 There should be total segregation of class-IV,
class-III and class-I power supply system.
4.6.2 D.G. rooms
shall be partitioned with 3 hour fire rating wall.
4.6.3 The design should facilitate frequent in-service
inspections and preventive maintenance for ensuring the uninterrupted
availability of power for plant.
4.6.4 Separate cable trenches shall be provided for
laying of power and control/ instrumentation cables.
4.6.5 Diverse cable routes shall be followed for
group-A and group-B cables of safety related systems.
4.6.6 The enhancement of electrical system’s safety
shall be maintained by using requisite quality materials and equipments.
4.6.7 Fire and Smoke detectors shall be provided in
cable allies and at the top of electrical cables and panels (details given in
Fire protection system DBR of ROP).
4.7 Site specific requirements
The system design shall be suitable for the
following ambient conditions and the site environment:
1
1.1
|
Elevation
above sea level
Distance
from sea coast
|
Near
sea level
About
1500 mtrs.
|
2
|
Ambient
air temperature
|
|
2.1
|
Maximum
|
45°C
|
2.2
|
Average
daily (max.)
|
35°C
|
2.3
|
Design
temperature for electrical equipments
|
45°C
|
3
|
Relative
Humidity
|
|
3.1
|
Maximum
|
98%
|
3.2
|
Design
RH for electrical equipments
|
98%
|
4
|
Maximum
RH and temperature occurring simultaneously
|
80% and
40°C resp.
|
5
|
Air
Quality
|
Clean
|
6
|
Seismic
data
|
Zone 2
on seismic scale
|
7
|
Soil
resistivity
|
100
ohm-m
|
8
|
Available
off-site power source
|
2 nos.
of adequately rated 33 KV, 1500 MVA feeders
|
4.8 Standardization
of design
4.9 4.8.1 The system engineering should adopt
reliable, easy-to-maintain type of equipment so that maintenance work can be
carried out safely and quickly. The equipments/ components/ materials used
should be of tested and of proven performance, supplied by manufacturers of
established reputation.
4.8.2 The system components and the equipments shall
be of proven design and duly qualified for the application involved.
4.8.3 The equipment and the materials shall be so
standardized that stock of inventory for O&M can be minimized to the extent
possible.
4.10
Design changes/ improvements over
previous plants
Following changes and improvements are envisaged in
design of electrical systems as per ASPRC recommendations, various plants’s
feedbacks and site constraints.
4.9.1 Dry type
Cast Resin/ resin impregnated power and Distribution transformers shall be used
in place of oil filled transformers for enhancement of system safety and the
reliability.
4.9.2 It is
proposed to provide a remote control centre through SCADA system for substations,
MCCs/ PCCs etc. preferably to be extended to the main control room for better
co-ordination amongst the operating staff and also to reduce manpower. State of
the art protective devices viz. Numerical relays shall be used for sub-station
equipments. Qualification verification and reliability analysis have been
carried out for the numerical relays for its suitability under Indian
conditions.
4.9.3 Variable Voltage Variable Frequency (VVVF)
drives shall be provided for all the ACVE system, Utilities & Services
system equipments and also for some major motor pump sets for speed/flow
control and the resultant energy conservation.
4.9.4 A PLC based Emergency Transfer system is
envisaged for automatic sequential starting of all class III loads during power
outage of Mains power supply.
4.9.5 Lighting transformer shall be provided for
isolation purpose for high block as well as sub-station & low block. Power
supply for lighting can be made available from the dedicated 415/415 V, 3 phase
AN type isolating transformer of adequate rating.
4.9.6 A separate common utility control room shall be
provided for the remote control of all the utilities and services of the plant.
4.9.7 Process cells shall be equipped with ‘SON’
lights through shielding plugs (with drawable type). ‘Gold plated’ 230V plug
receptacles with local switch shall be provided in cells for maintenance. The
shielding plug light shall be designed to withstand total cumulative dose of
100 MR.
4.9.8 16 kA SPN MCBs shall be provided for lighting
& plug-circuits with separate neutral for each circuit . Also, HFFR wires
shall be used for building electrification.
4.9.9 All major load centers shall have independent
Motor Control Centres (MCC) for the group-A and group-B motors in equal number,
for enhancement of reliability and redundancy.
4.9.10 Power Factor Improvement (PFI) capacitor banks
are planned in ROP sub-station, distributed on both the buses of 415 V Class IV
switchgear, and also at the major load centres.
4.9.11 All the important emergency power systems
including DG sets, DG control panels &
auxiliaries, Class III switchgears, redundant Motor Control Centres, UPS
systems, DC battery Banks, ACVRs etc. shall be physically separated to avoid
common mode failures.
4.9.12 Stainless Steel fixtures shall be used for
areas likely to have acid fumes such as Tank Space, Make-up Area etc.
4.9.13 XLPE insulated, FRLS inner and outer sheathed
cables shall be used in 415 V AC and 110 V/ 48 V DC systems.
4.9.14 HFFR wires shall be used for the building
electrification of low and high block building.
4.9.15 Armored cables are to be used for all the
outdoor applications and in-door applications, as applicable. All single core
AC circuit cables will have aluminum armoring, otherwise round galvanized steel
wire armoring shall be used for other systems’ cables.
4.9.16 Energy conservation in lighting shall be
achieved through the use of CFLs, low loss/ electronic ballasts/ inverters. Also,
‘PID’ control shall be used for 50% ‘Normal’ lights in sampling gallery/ isolating
corridor for energy saving.
4.9.17 Suitable Tie- lines are provided for 415V ROP
class-IV switchgear with the class-IV switchgear of PREFRE substation to
facilitate sharing of power between ROP & PREFRE, during system failures under administrative
controls.
4.10.1 Necessary
interlocking between breakers and auto load transfer facility shall be
provided.
4.10.2 All the components and panels of
the emergency control room (located in high block building of R.O.P.)
including class-II UPS systems, shall be seismically qualified for SSE (Safe
Shutdown Earthquake) level of earthquake as per IEEE-344 standards. Electrical system shall
otherwise conform to IS-1893 for seismic requirements.
4.10.3 In view of low smoke densities and
high radiation resistance, Chloro Sulphonated
polyethylene (CSPE) has been provided as
sheathing material for power and control cables installed
in process cells and other highly
radioactive areas. Flame Retardant Low Smoke Polly Vinyl
Chloride (FRLS-PVC) sheathed cables have
been used in control room and other critical areas.
4.10.4 Earth mat network having stranded
copper conductor with spacing of 11 meters between the
parallel conductors forming grid has been
provided for grounding system of the plant.
4.10.5 All the structures under ROP
Project, including the stack, have been
covered under the
lightning protection system adopted for the
plant.
4.10.6 All the
major load centers shall be segregated from each other so that planned or
non-planned
5.0 METHODS & TECHNIQUES:
5.1 Two 33
kV(E), 400 sq. mm. 3 core under ground
cable feeders from MSEB/ TAPS-1 & 2
switchyard, taken from two different bus sections shall feed 33 KV switchgears of ROP sub-station for
distribution of 33 KV power supply for PREFRE substation, ROP substation
and proposed UNCF substation.
5.2 Substation shall be
provided with ventilation air through supply air duct. Sub station control room shall have split air conditioner or
split chilled water- fan coil unit sets for ensuring smooth functioning of sophisticated softwares and
hardwares.
5.3 Transformers
room shall be provided with roof at top at about 5.5 m height. Transformer
rooms
shall be
partitioned with each other.
5.4 The layout of the power distribution centres
should be such as to avoid lengthy cabling so that
voltage drops
can be minimized with consequent improved performance of plant equipment.
5.5 Monorails
with chain pulley blocks are required in electrical workshop, DG room, lift
rooms.
5.6 Installation of
electrical PCC/MCCs/PDBs,
Distribution panels and
control panels shall be
made in separate
and readily accessible areas, rooms/ enclosures attached to the plant areas such as tank space, access
galleries, off gas rooms, FHA, labs, so
as to avoid their exposure
to the corrosive &
radio-active environment.
5.7 All electrical motors shall be connected through
DOL type starter but for E2 fan motors, which
will have VVVF drives. Running hour meter shall be
provided for all the utility & services system motors.
5.8 There should be provision of fire and smoke
sensors in cable allies and top of electrical cables/
panels.
5.9 Fire breaks/
barriers shall be provided wherever the cable crosses the floor/ ceiling.
5.10 There should be sealing on hume pipe sleeves
meant for cable entry(s) into the plant
buildings
(as anti-flood measures).
5.11 Separate cable routes/ trays shall be provided
for laying of power and control/ instrumentation
cables.
6.0
SYSTEM
CONFIGURATION
6.1
CLASS-IV POWER SUPPLY SYSTEM
Reliable ‘mains’
class-IV power supply is required for normal operation and maintenance of the
plant.
Two 33 kV
under ground cable feeders from
MSEB/ TAPS-1 & 2 switchyard,, taken from two different bus sections shall
feed the ROP sub-station through 33 kV
switchgear to be housed in new indoor substation as per single line diagram/ drawing no.1. The ROP sub-station will provide 415 V, 3 phase, 4 wire A.C. power
supply to all the plant loads. These two
33 KV HT incoming feeders to ROP HT switchgear will be used for ROP site,
ensuring practically two independent sources of power supply to the plant.
The following equipments are planned in an indoor ROP
sub-station for the class IV power system :
(1) 33 kV Vacuum circuit breakers .
(2) SCADA based switchgear system for 33 kV and
415 Volt power system.
(3) 33/ 0.433 kV, 2.5 MVA Dry type
transformers.
6.2
CLASS-III POWER SYSTEM
Some of the
equipment of the plant such as the exhaust & off-gas fans; part of the
lighting in the active areas of the plant; installed health physics instruments
and some of the vital in-process control/measurement instruments have to be
available all the time on considerations of plant and personnel safety. For
this purpose, class-III power system has been provided.
‘Emergency’ DG sets backed up class-III power supply
is required for operation of such safety
related and important loads of plant during outage of
class-IV power supply.
Two numbers of diesel generator sets of approximately 1010 kVA capacity each, shall
provide 415 V, 50 HZ grounded AC power supply
to safety related loads during
class-IV power failure/outage conditions
through a network independent of the class-IV power distribution. The
total emergency power requirement of the ROP Project/AWTF is estimated at about
850 kVA.
The class-IV and class-III load particulars are given
in Table-II & III respectively.
6.3 CLASS-II
POWER SYSTEM
Two independent 230 V, 50 kVA, AC single phase
class-II uninterruptible power supply (UPS) set shall be provided for critical
control systems viz. SCADA system, Public Address System, criticality monitors,
control instruments, turnstile gates etc.
Two class-III power feeders shall be dedicated for the UPS system for
continuous availability of power supply to these critical systems. Class-II
load list is tabulated in Table-IV.
6.4 CLASS-I POWER SYSTEM
Critical control instruments and auxiliary loads of
the plant need class-I DC power supply. These will be fed continuously with DC
power through the ACVR backed up by storage batteries.
The exit lighting provided in the main control
room/other control centres and at all the escape/exit routes of the plant shall
be connected to this power system. During emergency situations and class-IV
power failure conditions, these lights come on automatically before the Diesel
Emergency Power system takes over. This power system is categorized as class-I.
Two battery banks, each of 110 V (nominal), 425 AH, 56 Cell YKP 35 plante type,
shall provide Class-I, 110 V DC power supply to DC loads, in the event of
non-availability of Class IV or Class III power supply on DC switchboard /ACVR
terminals. Battery banks of 24V DC shall be provided for DG controls. Class-I
DC load list is tabulated in Table-V.
7.0 SYSTEM DESCRIPTION
7.1 INCOMING POWER SUPPLY TO ROP SUBSTATION
Two 33 kV
overhead MSEB lines are terminated in MSEB/NPC tapyard behind PREFRE complex. 2
nos. underground 400 sq. mm 3 core XLPE armoured cables are laid from the new
switch yard to ROP HT switchgear. These two 33 KV HT incoming feeders to ROP HT
switchgear will be used for ROP site, ensuring
practically two independent sources of power supply to the plant.
These two 33 kV feeder lines from MSEB/NPC switchyard,
taken from two different bus sections shall feed the ROP sub-station through 33 kV switchgear to be housed in new
indoor substation as per single line diagram/ drawing no. 1. The ROP
sub-station will provide 415 V, 3 phase, 4 wire ac
power supply to all the plant loads. Thus the plant
shall have practically two independent sources of power assuring a reliable
power supply.
7.2 SUB-STATION
The existing 33 kV outdoor switchyard provided in
PREFRE plant for receiving and distributing ‘Mains Class–IV’ power supply for
plant’s regular O&M needs, has 2 Bulk-oil circuit breaker and gang-operated
switches with drop-out type fuses for protecting the complete Mains power
system, which were installed during early 70’s. These designs are outdated,
unreliable and inadequate to provide protections as per safety codes. Also,
some of these devices have become unsafe and inoperable due to heavy corrosion,
wear & tear under salt-laden atmosphere. Due to above reasons and because
of their inadequate capacity to meet the enhanced load requirements of PREFRE
plant and ROP project, it has been decided to renovate the complete power
system of the plant by providing the following equipments of state-of-art
technologies in an indoor ROP sub-station :
(1) 33 kV Vacuum circuit breaker.
(2) SCADA based switchgear system for 33 kV
and 415 Volt power system.
(4) 33/ 0.433 kV, 2.5 MVA Dry type
transformers.
(5) 2 nos., 1010 KVA, 3 phase, 433V D.G. sets.
(6) A static, high efficiency class-II UPS
system for plant’s critical requirements.
(7) Class-I power system for managing total
blackout condition in the plant.
The layout of the sub-station shall be such that the
load centres are close to the sub-stations thereby avoiding lengthy cabling.
Consequently, voltage drops are expected to be minimal with improved equipment
performance. The sub-station is indoor, non-exposed type. XLPE cables shall be
laid through accessible cable trenches for interconnection of transformers and
HT switchgears
ROP sub-station
building is planned behind PREFRE Low Block building by demolishing the
existing outdoor 33 kV PREFRE switchyard. The low block building accommodates
most of the utilities/services systems of PREFRE and ROP. This substation will
thus feed major electrical loads like V2- fans, refrigeration compressors
etc. HT switch gears and the storage
batteries for the DC power supply shall also be located in this sub-station.
This sub-station shall also cater to the process loads and the exhaust
fans. The two diesel generators that
supply emergency power to the plant shall also be installed in this
sub-station.
7.2.1 SALIENT
FEATURES OF R.O.P. SUB-STATION
7.2.1.1
Physical separation of
class-IV, class-III, class-II and class-I power supply systems.
7.2.1.2 Risk of
fire hazards is avoided by using cast resin power transformers and vacuum
circuit breakers.
7.2.1.3 Physical
separation of class-III emergency bus
sections.
7.2.1.5
Separate
cable routings for class-IV, class-III, class-II and class-I power and control cables.
7.2.1.6 All cables have FRLS (Fire resistance low
smoke) inner and outer sheaths.
7.2.1.8 PLC
based auto sequential starting of
loads.
7.2.1.9
.Improvement of power factor by using APFC (Automatic power factor correction)
panels.
7.2.1.10
Substation control room shall have SCADA based data management and
control.
7.3 CLASS-IV
POWER SUPPLY SYSTEM
7.3.1 TRANSFORMERS (GENERAL FEATURES)
The power
transformers for ROP electrical system shall be of in-door, cast resin
encapsulated, epoxy impregnated, dry type and air cooled type. The transformers
shall have essential protective devices for safe and reliable operation.
Two number of transformers (33 kV/0.433 kV, 2500 kVA
rating) shall be installed in sub-station. The transformers can withstand the
maximum rated current at -2.5% tap on HV side and they can also withstand 110%
continuous overflowing. They shall be capable of withstanding 3 starts per hour
(under hot conditions) at DOL starting of highest rating motors with maximum
base load. Maximum noise level of the 2500 kVA transformer is 65 dB. The
neutral point of star connection can withstand highest over current. They are
equipped with winding temperature controllers. Core, windings, terminals, tap changers,
auxiliaries shall be designed for continuous and short time overload capacity.
It gives maintenance free operation. It has highest level of safety measures.
The transformers are class-H insulated cast resin system. Cast resin offers
high mechanical strength, improved earth tracking resistance, high dielectric,
moisture repellent and flame retardant qualities. The transformers shall have
‘Over current’, ‘Earth fault’, REF (Restricted Earth Fault) and winding
temperature protection using RTDs. Technical particulars of Dry type transformers
are listed in Table VI.
The transformer rooms shall be provided with roof at
the top. They are isolated from each other by the partitioning walls so that in
the event of fire, it’s spread can be avoided. Provision of exhaust fans may
also be available for better ventilation of the room.
1.0 INTRODUCTION:
Project ROP (Revamping of Power
Reactor Fuel Reprocessing (PREFRE) plant) at Tarapur is a radio chemical
facility with a reprocessing capacity of 100 Te of spent fuel, which is aimed
to facilitate life extension and the capacity augmentation of the existing
PREFRE plant at Tarapur. Power Reactor Fuel Reprocessing (PREFRE) plant was
designed, built and commissioned in 1974, to re-process the spent fuels from
CIRUS, RAPS, NAPS and MAPS reactors. As the existing PREFRE plant is nearly
three decades old, its process systems and the auxiliary support systems like
effluent handling in tanks, the piping network, waste storage etc. are proposed
to be up-graded through the ROP Project. Also as some new atomic power stations
have been recently commissioned at Kakrapara, Kaiga and Kota, capacity
augmentation of PREFRE is planned through the ROP project within the PREFRE
complex.
Owing to the
nature of processes employed, which involve handling of highly radioactive
process solutions, efficient performance of the Electrical Power system is
critical to plant safety. Availability
of a reliable and adequate Mains power supply is very critical for safe
operation of the plant. Similarly the emergency power supply systems need a
high degree of reliability for plant safety and environment protection.
2.0 SCOPE OF THE DESIGN BASIS REPORT
This Design Basis Report
covers mainly design
criteria, system description, salient
features of
components electrical system
of ROP sub-station, criteria for selection of safety
and non-safety
related electrical equipments, postulated initiating events and their consequences
on safety related
systems to meet
their intended functions. Separate DBR has been prepared for ROP facility.
3.0 DESIGN
OBJECTIVES
3.1 Class-IV
Mains Power Supply System (33 KV)
33KV `Mains’ HT power system shall be designed to
provide 33 KV mains power to ROP, PREFRE and proposed UNCF.
3.2 Class-IV Mains Power Supply System (415 V)
415V `Mains’ LT power system shall be designed to meet
the needs of class-IV power supply of projects ROP, AWTF and SFSF.
3.3
Class-III
power for ROP, AWTF & SFSF
The system design
shall ensure availability of class-III power supplies for ROP, AWTF and SFSF
projects.
3.4
Class-II
Power Supply System (230 V)
The system shall
be designed to meet the needs of 230V, class-II power supplies (UPS) for
C&I loads of ROP project.
3.5
Class-I
DC Power Supply System (110 V)
The system shall
be designed to meet the needs of 110V, DC class-I power supplies for switchgear
controls and exit lights of ROP project.
3.6 To ensure safety of plant and the O&M
personnel
System design
shall ensure the safety of plant equipment and that of operating/ maintenance
personnel during normal as well as emergency conditions like power
outages, flooding and outbreak of fire.
3.7 To provide adequate illumination levels
The design shall
ensure adequate illumination levels in the plant areas for ease of operation
and maintenance.
3.8 To ensure Continuous availability of Power
Electrical design
facilitates periodic in-service inspections and preventive maintenance for
ensuring availability of power to the important plant systems.
3.9 To reduce man-rem expenditures.
The design shall
facilitate remote maintenance for the electrical equipments planned to be
installed in the radioactive areas, so
as to reduce man-rem expenditures.
3.10 To enhance
system safety
Enhancement of
system safety by using requisite quality materials/ equipments.
3.11 Provisions for Future Expansions
The system design
shall have provisions for expansion and up gradations in future.
4.0 DESIGN CRITERIA
The
ROP electrical system shall be designed to meet the following criteria :-
4.1 Load
requirements: HV systems
4.1.1 The entire 33KV ‘Mains’ HT power system shall be
designed for catering to a total power requirement of about 15 MVA at a fault
level of 1500 MVA to feed and provide electrical power to PREFRE, ROP and
proposed UNCF substations for normal Operation and Maintenance of these plants.
The 33 kV Mains incomers shall be capable of meeting this power requirement
independently.
4.2 Load
requirements: LV systems
4.2.1 The 415 Volt electrical system consisting of
Class IV power supply system, Class III power supply system, Class II power
supply system and Class I power supply system shall be capable of meeting the
class-IV power requirement of about 2455 kVA, class-III power requirement of
about 850 kVA, class-II power requirement of about 41 kVA and class-I power requirement
of about 25 kW or 350 A for half an hour.
4.3 References/
Guidelines
The compliance of following codes shall be ensured :
-Indian
Electricity Rules
-NEC-85
-AERB Codes
(SGD-11) & guides
-Latest
applicable IS & IEEE standards.
The detailed reference list is given in Annexure-1.
4.4 Classification
of power supplies
The following
power supply systems have been envisaged at ROP substation to meet
operational & safety requirements:
4.4.1 Class-IV power supply: Alternating current power supply to meet
plant’s O&M loads & the auxiliaries, which can tolerate prolonged
interruption without affecting safety of the plant, is classified as Class-IV
Power Supply. 415 Volt mains supply has been provided from ROP substation. Two
33KV under ground cable feeders have been brought to the ROP substation from
MSEB/NPCIL’s 220 KV switchyard to meet Class-IV power requirement of entire site.
33KV power supply is further stepped down to 415 Volt class IV power in
the indoor ROP substation, from where
415 V power is distributed to the ROP,
AWTF & SFSF facilities.
4.4.2 Class-III power supply: Alternating current power supply to safety
related systems, that can tolerate short interruptions (up to 2 minutes) is
classified as Class-III power supply. Under normal conditions, this power
supply is derived from Class-IV and in case of loss of Class-IV power supply,
standby DG sets are automatically started and connected to the Class-III
switchgear systems through AMF logic to meet emergency power requirements of
the plant. The diesel generators and the Class-III switchgear systems are
provided in the indoor ROP substation, from where 415 V CLASS III power is
distributed to the ROP, AWTF & SFSF facilities.
4.4.3 Class-II
power supply: Critical
control systems viz. Public Address System, criticality monitors, control
instruments etc. powered through UPS
shall be available continuously. UPS for class II power supply system are
provided at the ROP high block building.
4.4.4 Class-I power supply:
Direct current power supply to loads which require direct current power is
called Class-I power supply. Normally direct current power is derived through
an AC to DC rectifier connected to Class-III power supply. Battery back up is
provided so that direct current power supply continues to be available even
when Class-III power or rectifier fails. Class-I power supply shall be provided
in the ROP sub-station.
The break-up of individual
maximum demand of above mentioned power supply systems of ROP project is as
under:
HIGH BLOCK BUILDING
Class-IV Class-III Class-II Class-I
1000 KVA 495KVA 40KVA 10 KW
LOW BLOCK BUILDING
Class-IV Class-III Class-II Class-I
40 KVA 5 KVA 1 KVA (16 KW) 1 KW
SERVICE BUILDINGS
Class-IV Class-III Class-II Class-I
600 KVA 100KVA - 1 KW
The load list of
class-IV, class-III, class-II and class-I power systems of ROP project are given
in Table-II, Table-III,
Table-IV and Table-V
respectively.
4.5 Functional
requirements
4.5.1 The design shall ensure quality power for the
electrical drives and devices through two independent mains power
supply and by using safe, reliable, energy efficient
and easy to maintain type system components and the associated
distribution network.
4.5.2 The permissible steady state voltage and
frequency limits (in terms of maximum, minimum & percentage) for
continuous operation of equipments connected to
various voltage levels are indicated below:
System Voltage
|
Permissible values
|
System Frequency
|
Permissible values
|
||||
Maximum
|
Minimum
|
Range in %
|
Maximum
|
Minimum
|
Range in %
|
||
Class IV
& class III
|
|||||||
415 V(AC)
|
439.9 V
|
390.1 V
|
± 6 %
|
50Hz
|
51.5Hz
|
48.5Hz
|
± 3%
|
230V
AC
|
243.8 V
|
216.2 V
|
± 6 %
|
50Hz
|
51.5Hz
|
48.5Hz
|
± 3%
|
Class II
|
|||||||
230V AC
|
235.75V
|
224.25V
|
± 2.5%
|
50Hz
|
50.5 Hz
|
49.5 Hz
|
± 1%
|
Class I
|
|||||||
110V DC
|
112.75 V
|
97.25 V
|
± 2.5%
|
|
|
|
|
4.5.3 The permissible
transient state voltage
and frequency limits ( in terms of
maximum,
minimum & percentage) for
continuous operation of equipments connected to various voltage levels
are indicated below:
System Voltage
|
Expected Transient Voltage Variation
|
Expected Transient Frequency
Variation
|
||||
Magnitude
|
Percentage
|
Recovery
Time
|
Magnitude
|
Percentage
|
Recovery
Time
|
|
Class-IV
|
556 V
|
+34%
|
50 msec.
|
54.25Hz
|
+8.5%
|
15
sec. To
|
415 V AC
|
290.5
V
|
-30%
|
200 ms.
|
|
|
52.5 Hz
|
|
|
|
|
|
|
|
Class-III
|
556.1 V
|
+34%
|
50 msec.
|
54.25Hz
|
+8.5%
|
15 sec. to
|
415 V AC
|
498 V
|
+20%
|
2.4 sec
|
52.5Hz
|
+5%
|
52.5 Hz
|
|
332 V
|
-20%
|
2.4 sec.
|
47.5Hz
|
-5%
|
2.4 sec.
|
|
|
|
|
|
|
|
Class–II
|
253 V
|
+10%
|
50 msec.
|
51Hz
|
+2%
|
----
|
230 V AC
|
207 V
|
-10%
|
50
msec.
|
49Hz
|
-2%
|
----
|
Class–I
|
112.75 V
|
+2.5%
|
50 msec.
|
-
|
-
|
----
|
110 V AC
|
97.25 V
|
-2.5%
|
50
msec.
|
-
|
-
|
----
|

4.5.4 The short circuit fault level at various buses i.e. 33 KV, 415V
class-IV, 415V class-III, 240V class-II and 110 V DC class-I is indicated
below:
|
|
|
Required rating for SWGR.
|
Switchgear Rating
|
||
Sl. No.
|
System
|
Fault Level for the bus
|
Making level
|
Symmetrical
Interrupting Level/withstand capacity
|
Making level
|
Symmetrical
Interrupting Level/withstand capacity for 1 sec.
|
1.
|
33 KV AC
Class-IV system
|
17.5 KA (rms)
|
36.75 kA
|
17.5 KA (rms)
|
52.75 kA
|
25 KA (rms)
|
2.
|
415 Volt AC
Cl-III, Cl-II & Cl-IV with Cl-III to Cl-II tie CB closed
|
52.5KA (rms)
|
110.77 KA peak
|
52.5 KA (rms)
|
137KA peak
|
65 KA (rms)
|
|
|
|
Required
rating for SWGR.
|
Switchgear
Rating
|
||
Sl. No
|
System
|
Fault Level for the bus
|
Making level
|
Symmetrical Interrupting Level/withstand capacity
|
Making level
|
Symmetrical
Interrupting Level/withstand capacity for 1 sec.
|
3.
|
Power DC
battery
|
9.4 KA
|
----
|
9.4 KA
|
----
|
20 kA
|
The above
table indicates the interrupting ratings of switchgear provided at various
voltage level.
From this
data it can be seen that the ratings are adequate with adequate margins.
4.5.5 33 KV/433
Volt transformers are provided with off circuit tap links having ±5% range. The
table below gives the terminal voltage for various load conditions for constant
input voltage.
Sr.No.
|
Grid
Voltage
|
Load
as % of full load
|
Secondary
voltage at rated tap
|
Required
tap position
|
Expected
secondary voltage
|
1.
|
33 KV
|
|
|
|
|
1.1
|
|
0%
|
433 V
|
Rated tap
|
433 V
|
1.2
|
|
50%
|
415.6 V
|
Rated tap
|
415.6 V
|
1.3
|
|
100%
|
398.3 V
|
-2.5%
|
444V
|
2.
|
33 KV+12%
|
|
|
|
|
2.1
|
|
0%
|
484.96V
|
+5%
|
461.8V
|
2.2
|
|
50%
|
465.56V
|
+5%
|
443.3V
|
2.3
|
|
100%
|
446.16V
|
+5%
|
424.8V
|
3.
|
33 KV-9%
|
|
|
|
|
3.1
|
|
0%
|
394V
|
-5%
|
414.7V
|
3.2
|
|
50%
|
378V
|
-5%
|
398.1V
|
3.3
|
|
100%
|
362.5V
|
-5%
|
381.5V
|
From the above
table, it can be observed that steady state 433V bus voltage is maintained for
the expected voltage variation on 33 KV side and various load conditions.
4.5.6 The class-III power supply should automatically
come on stream when the class-IV power supply fails due to any reason. All the
essential base loads like lighting, health and safety instruments, plant
communication equipment etc., should be energized within time duration of 30
–100 seconds. Power supply for all other bulk loads like exhaust and off-gas
fans should be made available within a time span commensurate with the health
and safety requirement.
4.5.7 Rating of the two DG sets shall be so chosen
that the entire class-III loads of the plant can be continuously fed even if
one of the sets is not available.
4.5.8 Bulk-oil
storage facility for DG Room shall be common for ROP, PREFRE & IP-1, which
shall be suitably located between PREFRE and IP-1 and shall be about 15m away
from any adjacent structure. Day tanks for ROP DG sets are to be near ROP
substation adjacent to the furnace oil storage bldg.
4.5.9
In most of the plant areas, 30-40% of the lights installed shall be
provided with class-III power supply whereas in control room, 50% of the lights
installed shall be provided with class-III power supply & rest from
class-II. Some of the plant facilities shall have special lighting provisions
such as 250 W HPSV/ 500 W halogen lamp fixtures for fuel pond lighting,
150/250W high pressure sodium vapour lamps in the dissolver cell, 250 W HPSV
for process cells, 35W/55 W SOX/ 18 W CFL for Hot cell & Blister (cubicles)
lighting Flame proof fixtures with ML lamps for inflammable material stores. All
the distribution boards have been provided with a 25% diversity factor.
4.5.10 The instrument power distribution
board (IPDB) providing control power supplies to various instruments in control room,
shall be fed with two feeders of Class II power. Each feeder shall be capable
of meeting the entire instrumentation load. Duplication of feeders is to
enhance the reliability and availability of power supply for the
instrumentation system.
4.5.11 Class-I DC power supply to critical
control relays, instruments & sub-station auxiliary loads shall be fed
continuously through DC switchboard receiving power normally from the ACVRs and
backed up with storage batteries.
4.5.12 Battery banks shall be adequately
designed to supply the entire class-I power requirement for a period of 30
minutes at high discharge rates without affecting the life of batteries.
4.5.13 In the event of non availability of
Class IV or Class III power supply to ACVRs, or during failure of ACVRs, the
batteries take over the function of feeding DC power to plant's critical loads
like switch gear controls, indications, communication system and also to the DC
`EXIT’ lighting along the evacuation routes in active areas.
4.5.14 The system design should ensure the
safety of plant equipment and that of the operating /maintenance personnel not
only during normal operation but also during emergency conditions like outbreak
of fire.
4.5.15 The design should be such that all
important process loads can be controlled from the main control room. Indication
of the availability of power supplies and ON/OFF status of major loads should
also be available at the control room.
4.5.16 The layout of the power distribution
centers should be such as to avoid lengthy cabling so that voltage drops can be
minimized with consequent improved performance of plant equipment.
4.5.17 All major load centres should be
segregated from each other so that planned or non- planned power interruption
in one area does not affect the operation in other areas.
4.5.18 All electrical motors shall be
connected through DOL type starter but for E2 fan motors
which will have VVVF drives.
4.5.19 Design shall facilitate control of
all important process loads from main control room.
4.6 Safety
requirements
4.6.1 There should be total segregation of class-IV,
class-III and class-I power supply system.
4.6.2 D.G. rooms
shall be partitioned with 3 hour fire rating wall.
4.6.3 The design should facilitate frequent in-service
inspections and preventive maintenance for ensuring the uninterrupted
availability of power for plant.
4.6.4 Separate cable trenches shall be provided for
laying of power and control/ instrumentation cables.
4.6.5 Diverse cable routes shall be followed for
group-A and group-B cables of safety related systems.
4.6.6 The enhancement of electrical system’s safety
shall be maintained by using requisite quality materials and equipments.
4.6.7 Fire and Smoke detectors shall be provided in
cable allies and at the top of electrical cables and panels (details given in
Fire protection system DBR of ROP).
4.7 Site specific requirements
The system design shall be suitable for the
following ambient conditions and the site environment:
1
1.1
|
Elevation
above sea level
Distance
from sea coast
|
Near
sea level
About
1500 mtrs.
|
2
|
Ambient
air temperature
|
|
2.1
|
Maximum
|
45°C
|
2.2
|
Average
daily (max.)
|
35°C
|
2.3
|
Design
temperature for electrical equipments
|
45°C
|
3
|
Relative
Humidity
|
|
3.1
|
Maximum
|
98%
|
3.2
|
Design
RH for electrical equipments
|
98%
|
4
|
Maximum
RH and temperature occurring simultaneously
|
80% and
40°C resp.
|
5
|
Air
Quality
|
Clean
|
6
|
Seismic
data
|
Zone 2
on seismic scale
|
7
|
Soil
resistivity
|
100
ohm-m
|
8
|
Available
off-site power source
|
2 nos.
of adequately rated 33 KV, 1500 MVA feeders
|
4.8 Standardization
of design
4.9 4.8.1 The system engineering should adopt
reliable, easy-to-maintain type of equipment so that maintenance work can be
carried out safely and quickly. The equipments/ components/ materials used
should be of tested and of proven performance, supplied by manufacturers of
established reputation.
4.8.2 The system components and the equipments shall
be of proven design and duly qualified for the application involved.
4.8.3 The equipment and the materials shall be so
standardized that stock of inventory for O&M can be minimized to the extent
possible.
4.10
Design changes/ improvements over
previous plants
Following changes and improvements are envisaged in
design of electrical systems as per ASPRC recommendations, various plants’s
feedbacks and site constraints.
4.9.1 Dry type
Cast Resin/ resin impregnated power and Distribution transformers shall be used
in place of oil filled transformers for enhancement of system safety and the
reliability.
4.9.2 It is
proposed to provide a remote control centre through SCADA system for substations,
MCCs/ PCCs etc. preferably to be extended to the main control room for better
co-ordination amongst the operating staff and also to reduce manpower. State of
the art protective devices viz. Numerical relays shall be used for sub-station
equipments. Qualification verification and reliability analysis have been
carried out for the numerical relays for its suitability under Indian
conditions.
4.9.3 Variable Voltage Variable Frequency (VVVF)
drives shall be provided for all the ACVE system, Utilities & Services
system equipments and also for some major motor pump sets for speed/flow
control and the resultant energy conservation.
4.9.4 A PLC based Emergency Transfer system is
envisaged for automatic sequential starting of all class III loads during power
outage of Mains power supply.
4.9.5 Lighting transformer shall be provided for
isolation purpose for high block as well as sub-station & low block. Power
supply for lighting can be made available from the dedicated 415/415 V, 3 phase
AN type isolating transformer of adequate rating.
4.9.6 A separate common utility control room shall be
provided for the remote control of all the utilities and services of the plant.
4.9.7 Process cells shall be equipped with ‘SON’
lights through shielding plugs (with drawable type). ‘Gold plated’ 230V plug
receptacles with local switch shall be provided in cells for maintenance. The
shielding plug light shall be designed to withstand total cumulative dose of
100 MR.
4.9.8 16 kA SPN MCBs shall be provided for lighting
& plug-circuits with separate neutral for each circuit . Also, HFFR wires
shall be used for building electrification.
4.9.9 All major load centers shall have independent
Motor Control Centres (MCC) for the group-A and group-B motors in equal number,
for enhancement of reliability and redundancy.
4.9.10 Power Factor Improvement (PFI) capacitor banks
are planned in ROP sub-station, distributed on both the buses of 415 V Class IV
switchgear, and also at the major load centres.
4.9.11 All the important emergency power systems
including DG sets, DG control panels &
auxiliaries, Class III switchgears, redundant Motor Control Centres, UPS
systems, DC battery Banks, ACVRs etc. shall be physically separated to avoid
common mode failures.
4.9.12 Stainless Steel fixtures shall be used for
areas likely to have acid fumes such as Tank Space, Make-up Area etc.
4.9.13 XLPE insulated, FRLS inner and outer sheathed
cables shall be used in 415 V AC and 110 V/ 48 V DC systems.
4.9.14 HFFR wires shall be used for the building
electrification of low and high block building.
4.9.15 Armored cables are to be used for all the
outdoor applications and in-door applications, as applicable. All single core
AC circuit cables will have aluminum armoring, otherwise round galvanized steel
wire armoring shall be used for other systems’ cables.
4.9.16 Energy conservation in lighting shall be
achieved through the use of CFLs, low loss/ electronic ballasts/ inverters. Also,
‘PID’ control shall be used for 50% ‘Normal’ lights in sampling gallery/ isolating
corridor for energy saving.
4.9.17 Suitable Tie- lines are provided for 415V ROP
class-IV switchgear with the class-IV switchgear of PREFRE substation to
facilitate sharing of power between ROP & PREFRE, during system failures under administrative
controls.
4.10.1 Necessary
interlocking between breakers and auto load transfer facility shall be
provided.
4.10.2 All the components and panels of
the emergency control room (located in high block building of R.O.P.)
including class-II UPS systems, shall be seismically qualified for SSE (Safe
Shutdown Earthquake) level of earthquake as per IEEE-344 standards. Electrical system shall
otherwise conform to IS-1893 for seismic requirements.
4.10.3 In view of low smoke densities and
high radiation resistance, Chloro Sulphonated
polyethylene (CSPE) has been provided as
sheathing material for power and control cables installed
in process cells and other highly
radioactive areas. Flame Retardant Low Smoke Polly Vinyl
Chloride (FRLS-PVC) sheathed cables have
been used in control room and other critical areas.
4.10.4 Earth mat network having stranded
copper conductor with spacing of 11 meters between the
parallel conductors forming grid has been
provided for grounding system of the plant.
4.10.5 All the structures under ROP
Project, including the stack, have been
covered under the
lightning protection system adopted for the
plant.
4.10.6 All the
major load centers shall be segregated from each other so that planned or
non-planned
5.0 METHODS & TECHNIQUES:
5.1 Two 33
kV(E), 400 sq. mm. 3 core under ground
cable feeders from MSEB/ TAPS-1 & 2
switchyard, taken from two different bus sections shall feed 33 KV switchgears of ROP sub-station for
distribution of 33 KV power supply for PREFRE substation, ROP substation
and proposed UNCF substation.
5.2 Substation shall be
provided with ventilation air through supply air duct. Sub station control room shall have split air conditioner or
split chilled water- fan coil unit sets for ensuring smooth functioning of sophisticated softwares and
hardwares.
5.3 Transformers
room shall be provided with roof at top at about 5.5 m height. Transformer
rooms
shall be
partitioned with each other.
5.4 The layout of the power distribution centres
should be such as to avoid lengthy cabling so that
voltage drops
can be minimized with consequent improved performance of plant equipment.
5.5 Monorails
with chain pulley blocks are required in electrical workshop, DG room, lift
rooms.
5.6 Installation of
electrical PCC/MCCs/PDBs,
Distribution panels and
control panels shall be
made in separate
and readily accessible areas, rooms/ enclosures attached to the plant areas such as tank space, access
galleries, off gas rooms, FHA, labs, so
as to avoid their exposure
to the corrosive &
radio-active environment.
5.7 All electrical motors shall be connected through
DOL type starter but for E2 fan motors, which
will have VVVF drives. Running hour meter shall be
provided for all the utility & services system motors.
5.8 There should be provision of fire and smoke
sensors in cable allies and top of electrical cables/
panels.
5.9 Fire breaks/
barriers shall be provided wherever the cable crosses the floor/ ceiling.
5.10 There should be sealing on hume pipe sleeves
meant for cable entry(s) into the plant
buildings
(as anti-flood measures).
5.11 Separate cable routes/ trays shall be provided
for laying of power and control/ instrumentation
cables.
6.0
SYSTEM
CONFIGURATION
6.1
CLASS-IV POWER SUPPLY SYSTEM
Reliable ‘mains’
class-IV power supply is required for normal operation and maintenance of the
plant.
Two 33 kV
under ground cable feeders from
MSEB/ TAPS-1 & 2 switchyard,, taken from two different bus sections shall
feed the ROP sub-station through 33 kV
switchgear to be housed in new indoor substation as per single line diagram/ drawing no.1. The ROP sub-station will provide 415 V, 3 phase, 4 wire A.C. power
supply to all the plant loads. These two
33 KV HT incoming feeders to ROP HT switchgear will be used for ROP site,
ensuring practically two independent sources of power supply to the plant.
The following equipments are planned in an indoor ROP
sub-station for the class IV power system :
(1) 33 kV Vacuum circuit breakers .
(2) SCADA based switchgear system for 33 kV and
415 Volt power system.
(3) 33/ 0.433 kV, 2.5 MVA Dry type
transformers.
6.2
CLASS-III POWER SYSTEM
Some of the
equipment of the plant such as the exhaust & off-gas fans; part of the
lighting in the active areas of the plant; installed health physics instruments
and some of the vital in-process control/measurement instruments have to be
available all the time on considerations of plant and personnel safety. For
this purpose, class-III power system has been provided.
‘Emergency’ DG sets backed up class-III power supply
is required for operation of such safety
related and important loads of plant during outage of
class-IV power supply.
Two numbers of diesel generator sets of approximately 1010 kVA capacity each, shall
provide 415 V, 50 HZ grounded AC power supply
to safety related loads during
class-IV power failure/outage conditions
through a network independent of the class-IV power distribution. The
total emergency power requirement of the ROP Project/AWTF is estimated at about
850 kVA.
The class-IV and class-III load particulars are given
in Table-II & III respectively.
6.3 CLASS-II
POWER SYSTEM
Two independent 230 V, 50 kVA, AC single phase
class-II uninterruptible power supply (UPS) set shall be provided for critical
control systems viz. SCADA system, Public Address System, criticality monitors,
control instruments, turnstile gates etc.
Two class-III power feeders shall be dedicated for the UPS system for
continuous availability of power supply to these critical systems. Class-II
load list is tabulated in Table-IV.
6.4 CLASS-I POWER SYSTEM
Critical control instruments and auxiliary loads of
the plant need class-I DC power supply. These will be fed continuously with DC
power through the ACVR backed up by storage batteries.
The exit lighting provided in the main control
room/other control centres and at all the escape/exit routes of the plant shall
be connected to this power system. During emergency situations and class-IV
power failure conditions, these lights come on automatically before the Diesel
Emergency Power system takes over. This power system is categorized as class-I.
Two battery banks, each of 110 V (nominal), 425 AH, 56 Cell YKP 35 plante type,
shall provide Class-I, 110 V DC power supply to DC loads, in the event of
non-availability of Class IV or Class III power supply on DC switchboard /ACVR
terminals. Battery banks of 24V DC shall be provided for DG controls. Class-I
DC load list is tabulated in Table-V.
7.0 SYSTEM DESCRIPTION
7.1 INCOMING POWER SUPPLY TO ROP SUBSTATION
Two 33 kV
overhead MSEB lines are terminated in MSEB/NPC tapyard behind PREFRE complex. 2
nos. underground 400 sq. mm 3 core XLPE armoured cables are laid from the new
switch yard to ROP HT switchgear. These two 33 KV HT incoming feeders to ROP HT
switchgear will be used for ROP site, ensuring
practically two independent sources of power supply to the plant.
These two 33 kV feeder lines from MSEB/NPC switchyard,
taken from two different bus sections shall feed the ROP sub-station through 33 kV switchgear to be housed in new
indoor substation as per single line diagram/ drawing no. 1. The ROP
sub-station will provide 415 V, 3 phase, 4 wire ac
power supply to all the plant loads. Thus the plant
shall have practically two independent sources of power assuring a reliable
power supply.
7.2 SUB-STATION
The existing 33 kV outdoor switchyard provided in
PREFRE plant for receiving and distributing ‘Mains Class–IV’ power supply for
plant’s regular O&M needs, has 2 Bulk-oil circuit breaker and gang-operated
switches with drop-out type fuses for protecting the complete Mains power
system, which were installed during early 70’s. These designs are outdated,
unreliable and inadequate to provide protections as per safety codes. Also,
some of these devices have become unsafe and inoperable due to heavy corrosion,
wear & tear under salt-laden atmosphere. Due to above reasons and because
of their inadequate capacity to meet the enhanced load requirements of PREFRE
plant and ROP project, it has been decided to renovate the complete power
system of the plant by providing the following equipments of state-of-art
technologies in an indoor ROP sub-station :
(1) 33 kV Vacuum circuit breaker.
(2) SCADA based switchgear system for 33 kV
and 415 Volt power system.
(4) 33/ 0.433 kV, 2.5 MVA Dry type
transformers.
(5) 2 nos., 1010 KVA, 3 phase, 433V D.G. sets.
(6) A static, high efficiency class-II UPS
system for plant’s critical requirements.
(7) Class-I power system for managing total
blackout condition in the plant.
The layout of the sub-station shall be such that the
load centres are close to the sub-stations thereby avoiding lengthy cabling.
Consequently, voltage drops are expected to be minimal with improved equipment
performance. The sub-station is indoor, non-exposed type. XLPE cables shall be
laid through accessible cable trenches for interconnection of transformers and
HT switchgears
ROP sub-station
building is planned behind PREFRE Low Block building by demolishing the
existing outdoor 33 kV PREFRE switchyard. The low block building accommodates
most of the utilities/services systems of PREFRE and ROP. This substation will
thus feed major electrical loads like V2- fans, refrigeration compressors
etc. HT switch gears and the storage
batteries for the DC power supply shall also be located in this sub-station.
This sub-station shall also cater to the process loads and the exhaust
fans. The two diesel generators that
supply emergency power to the plant shall also be installed in this
sub-station.
7.2.1 SALIENT
FEATURES OF R.O.P. SUB-STATION
7.2.1.1
Physical separation of
class-IV, class-III, class-II and class-I power supply systems.
7.2.1.2 Risk of
fire hazards is avoided by using cast resin power transformers and vacuum
circuit breakers.
7.2.1.3 Physical
separation of class-III emergency bus
sections.
7.2.1.5
Separate
cable routings for class-IV, class-III, class-II and class-I power and control cables.
7.2.1.6 All cables have FRLS (Fire resistance low
smoke) inner and outer sheaths.
7.2.1.8 PLC
based auto sequential starting of
loads.
7.2.1.9
.Improvement of power factor by using APFC (Automatic power factor correction)
panels.
7.2.1.10
Substation control room shall have SCADA based data management and
control.
7.3 CLASS-IV
POWER SUPPLY SYSTEM
7.3.1 TRANSFORMERS (GENERAL FEATURES)
The power
transformers for ROP electrical system shall be of in-door, cast resin
encapsulated, epoxy impregnated, dry type and air cooled type. The transformers
shall have essential protective devices for safe and reliable operation.
Two number of transformers (33 kV/0.433 kV, 2500 kVA
rating) shall be installed in sub-station. The transformers can withstand the
maximum rated current at -2.5% tap on HV side and they can also withstand 110%
continuous overflowing. They shall be capable of withstanding 3 starts per hour
(under hot conditions) at DOL starting of highest rating motors with maximum
base load. Maximum noise level of the 2500 kVA transformer is 65 dB. The
neutral point of star connection can withstand highest over current. They are
equipped with winding temperature controllers. Core, windings, terminals, tap changers,
auxiliaries shall be designed for continuous and short time overload capacity.
It gives maintenance free operation. It has highest level of safety measures.
The transformers are class-H insulated cast resin system. Cast resin offers
high mechanical strength, improved earth tracking resistance, high dielectric,
moisture repellent and flame retardant qualities. The transformers shall have
‘Over current’, ‘Earth fault’, REF (Restricted Earth Fault) and winding
temperature protection using RTDs. Technical particulars of Dry type transformers
are listed in Table VI.
The transformer rooms shall be provided with roof at
the top. They are isolated from each other by the partitioning walls so that in
the event of fire, it’s spread can be avoided. Provision of exhaust fans may
also be available for better ventilation of the room.
1.0 INTRODUCTION:
Project ROP (Revamping of Power
Reactor Fuel Reprocessing (PREFRE) plant) at Tarapur is a radio chemical
facility with a reprocessing capacity of 100 Te of spent fuel, which is aimed
to facilitate life extension and the capacity augmentation of the existing
PREFRE plant at Tarapur. Power Reactor Fuel Reprocessing (PREFRE) plant was
designed, built and commissioned in 1974, to re-process the spent fuels from
CIRUS, RAPS, NAPS and MAPS reactors. As the existing PREFRE plant is nearly
three decades old, its process systems and the auxiliary support systems like
effluent handling in tanks, the piping network, waste storage etc. are proposed
to be up-graded through the ROP Project. Also as some new atomic power stations
have been recently commissioned at Kakrapara, Kaiga and Kota, capacity
augmentation of PREFRE is planned through the ROP project within the PREFRE
complex.
Owing to the
nature of processes employed, which involve handling of highly radioactive
process solutions, efficient performance of the Electrical Power system is
critical to plant safety. Availability
of a reliable and adequate Mains power supply is very critical for safe
operation of the plant. Similarly the emergency power supply systems need a
high degree of reliability for plant safety and environment protection.
2.0 SCOPE OF THE DESIGN BASIS REPORT
This Design Basis Report
covers mainly design
criteria, system description, salient
features of
components electrical system
of ROP sub-station, criteria for selection of safety
and non-safety
related electrical equipments, postulated initiating events and their consequences
on safety related
systems to meet
their intended functions. Separate DBR has been prepared for ROP facility.
3.0 DESIGN
OBJECTIVES
3.1 Class-IV
Mains Power Supply System (33 KV)
33KV `Mains’ HT power system shall be designed to
provide 33 KV mains power to ROP, PREFRE and proposed UNCF.
3.2 Class-IV Mains Power Supply System (415 V)
415V `Mains’ LT power system shall be designed to meet
the needs of class-IV power supply of projects ROP, AWTF and SFSF.
3.3
Class-III
power for ROP, AWTF & SFSF
The system design
shall ensure availability of class-III power supplies for ROP, AWTF and SFSF
projects.
3.4
Class-II
Power Supply System (230 V)
The system shall
be designed to meet the needs of 230V, class-II power supplies (UPS) for
C&I loads of ROP project.
3.5
Class-I
DC Power Supply System (110 V)
The system shall
be designed to meet the needs of 110V, DC class-I power supplies for switchgear
controls and exit lights of ROP project.
3.6 To ensure safety of plant and the O&M
personnel
System design
shall ensure the safety of plant equipment and that of operating/ maintenance
personnel during normal as well as emergency conditions like power
outages, flooding and outbreak of fire.
3.7 To provide adequate illumination levels
The design shall
ensure adequate illumination levels in the plant areas for ease of operation
and maintenance.
3.8 To ensure Continuous availability of Power
Electrical design
facilitates periodic in-service inspections and preventive maintenance for
ensuring availability of power to the important plant systems.
3.9 To reduce man-rem expenditures.
The design shall
facilitate remote maintenance for the electrical equipments planned to be
installed in the radioactive areas, so
as to reduce man-rem expenditures.
3.10 To enhance
system safety
Enhancement of
system safety by using requisite quality materials/ equipments.
3.11 Provisions for Future Expansions
The system design
shall have provisions for expansion and up gradations in future.
4.0 DESIGN CRITERIA
The
ROP electrical system shall be designed to meet the following criteria :-
4.1 Load
requirements: HV systems
4.1.1 The entire 33KV ‘Mains’ HT power system shall be
designed for catering to a total power requirement of about 15 MVA at a fault
level of 1500 MVA to feed and provide electrical power to PREFRE, ROP and
proposed UNCF substations for normal Operation and Maintenance of these plants.
The 33 kV Mains incomers shall be capable of meeting this power requirement
independently.
4.2 Load
requirements: LV systems
4.2.1 The 415 Volt electrical system consisting of
Class IV power supply system, Class III power supply system, Class II power
supply system and Class I power supply system shall be capable of meeting the
class-IV power requirement of about 2455 kVA, class-III power requirement of
about 850 kVA, class-II power requirement of about 41 kVA and class-I power requirement
of about 25 kW or 350 A for half an hour.
4.3 References/
Guidelines
The compliance of following codes shall be ensured :
-Indian
Electricity Rules
-NEC-85
-AERB Codes
(SGD-11) & guides
-Latest
applicable IS & IEEE standards.
The detailed reference list is given in Annexure-1.
4.4 Classification
of power supplies
The following
power supply systems have been envisaged at ROP substation to meet
operational & safety requirements:
4.4.1 Class-IV power supply: Alternating current power supply to meet
plant’s O&M loads & the auxiliaries, which can tolerate prolonged
interruption without affecting safety of the plant, is classified as Class-IV
Power Supply. 415 Volt mains supply has been provided from ROP substation. Two
33KV under ground cable feeders have been brought to the ROP substation from
MSEB/NPCIL’s 220 KV switchyard to meet Class-IV power requirement of entire site.
33KV power supply is further stepped down to 415 Volt class IV power in
the indoor ROP substation, from where
415 V power is distributed to the ROP,
AWTF & SFSF facilities.
4.4.2 Class-III power supply: Alternating current power supply to safety
related systems, that can tolerate short interruptions (up to 2 minutes) is
classified as Class-III power supply. Under normal conditions, this power
supply is derived from Class-IV and in case of loss of Class-IV power supply,
standby DG sets are automatically started and connected to the Class-III
switchgear systems through AMF logic to meet emergency power requirements of
the plant. The diesel generators and the Class-III switchgear systems are
provided in the indoor ROP substation, from where 415 V CLASS III power is
distributed to the ROP, AWTF & SFSF facilities.
4.4.3 Class-II
power supply: Critical
control systems viz. Public Address System, criticality monitors, control
instruments etc. powered through UPS
shall be available continuously. UPS for class II power supply system are
provided at the ROP high block building.
4.4.4 Class-I power supply:
Direct current power supply to loads which require direct current power is
called Class-I power supply. Normally direct current power is derived through
an AC to DC rectifier connected to Class-III power supply. Battery back up is
provided so that direct current power supply continues to be available even
when Class-III power or rectifier fails. Class-I power supply shall be provided
in the ROP sub-station.
The break-up of individual
maximum demand of above mentioned power supply systems of ROP project is as
under:
HIGH BLOCK BUILDING
Class-IV Class-III Class-II Class-I
1000 KVA 495KVA 40KVA 10 KW
LOW BLOCK BUILDING
Class-IV Class-III Class-II Class-I
40 KVA 5 KVA 1 KVA (16 KW) 1 KW
SERVICE BUILDINGS
Class-IV Class-III Class-II Class-I
600 KVA 100KVA - 1 KW
The load list of
class-IV, class-III, class-II and class-I power systems of ROP project are given
in Table-II, Table-III,
Table-IV and Table-V
respectively.
4.5 Functional
requirements
4.5.1 The design shall ensure quality power for the
electrical drives and devices through two independent mains power
supply and by using safe, reliable, energy efficient
and easy to maintain type system components and the associated
distribution network.
4.5.2 The permissible steady state voltage and
frequency limits (in terms of maximum, minimum & percentage) for
continuous operation of equipments connected to
various voltage levels are indicated below:
System Voltage
|
Permissible values
|
System Frequency
|
Permissible values
|
||||
Maximum
|
Minimum
|
Range in %
|
Maximum
|
Minimum
|
Range in %
|
||
Class IV
& class III
|
|||||||
415 V(AC)
|
439.9 V
|
390.1 V
|
± 6 %
|
50Hz
|
51.5Hz
|
48.5Hz
|
± 3%
|
230V
AC
|
243.8 V
|
216.2 V
|
± 6 %
|
50Hz
|
51.5Hz
|
48.5Hz
|
± 3%
|
Class II
|
|||||||
230V AC
|
235.75V
|
224.25V
|
± 2.5%
|
50Hz
|
50.5 Hz
|
49.5 Hz
|
± 1%
|
Class I
|
|||||||
110V DC
|
112.75 V
|
97.25 V
|
± 2.5%
|
|
|
|
|
4.5.3 The permissible
transient state voltage
and frequency limits ( in terms of
maximum,
minimum & percentage) for
continuous operation of equipments connected to various voltage levels
are indicated below:
System Voltage
|
Expected Transient Voltage Variation
|
Expected Transient Frequency
Variation
|
||||
Magnitude
|
Percentage
|
Recovery
Time
|
Magnitude
|
Percentage
|
Recovery
Time
|
|
Class-IV
|
556 V
|
+34%
|
50 msec.
|
54.25Hz
|
+8.5%
|
15
sec. To
|
415 V AC
|
290.5
V
|
-30%
|
200 ms.
|
|
|
52.5 Hz
|
|
|
|
|
|
|
|
Class-III
|
556.1 V
|
+34%
|
50 msec.
|
54.25Hz
|
+8.5%
|
15 sec. to
|
415 V AC
|
498 V
|
+20%
|
2.4 sec
|
52.5Hz
|
+5%
|
52.5 Hz
|
|
332 V
|
-20%
|
2.4 sec.
|
47.5Hz
|
-5%
|
2.4 sec.
|
|
|
|
|
|
|
|
Class–II
|
253 V
|
+10%
|
50 msec.
|
51Hz
|
+2%
|
----
|
230 V AC
|
207 V
|
-10%
|
50
msec.
|
49Hz
|
-2%
|
----
|
Class–I
|
112.75 V
|
+2.5%
|
50 msec.
|
-
|
-
|
----
|
110 V AC
|
97.25 V
|
-2.5%
|
50
msec.
|
-
|
-
|
----
|

4.5.4 The short circuit fault level at various buses i.e. 33 KV, 415V
class-IV, 415V class-III, 240V class-II and 110 V DC class-I is indicated
below:
|
|
|
Required rating for SWGR.
|
Switchgear Rating
|
||
Sl. No.
|
System
|
Fault Level for the bus
|
Making level
|
Symmetrical
Interrupting Level/withstand capacity
|
Making level
|
Symmetrical
Interrupting Level/withstand capacity for 1 sec.
|
1.
|
33 KV AC
Class-IV system
|
17.5 KA (rms)
|
36.75 kA
|
17.5 KA (rms)
|
52.75 kA
|
25 KA (rms)
|
2.
|
415 Volt AC
Cl-III, Cl-II & Cl-IV with Cl-III to Cl-II tie CB closed
|
52.5KA (rms)
|
110.77 KA peak
|
52.5 KA (rms)
|
137KA peak
|
65 KA (rms)
|
|
|
|
Required
rating for SWGR.
|
Switchgear
Rating
|
||
Sl. No
|
System
|
Fault Level for the bus
|
Making level
|
Symmetrical Interrupting Level/withstand capacity
|
Making level
|
Symmetrical
Interrupting Level/withstand capacity for 1 sec.
|
3.
|
Power DC
battery
|
9.4 KA
|
----
|
9.4 KA
|
----
|
20 kA
|
The above
table indicates the interrupting ratings of switchgear provided at various
voltage level.
From this
data it can be seen that the ratings are adequate with adequate margins.
4.5.5 33 KV/433
Volt transformers are provided with off circuit tap links having ±5% range. The
table below gives the terminal voltage for various load conditions for constant
input voltage.
Sr.No.
|
Grid
Voltage
|
Load
as % of full load
|
Secondary
voltage at rated tap
|
Required
tap position
|
Expected
secondary voltage
|
1.
|
33 KV
|
|
|
|
|
1.1
|
|
0%
|
433 V
|
Rated tap
|
433 V
|
1.2
|
|
50%
|
415.6 V
|
Rated tap
|
415.6 V
|
1.3
|
|
100%
|
398.3 V
|
-2.5%
|
444V
|
2.
|
33 KV+12%
|
|
|
|
|
2.1
|
|
0%
|
484.96V
|
+5%
|
461.8V
|
2.2
|
|
50%
|
465.56V
|
+5%
|
443.3V
|
2.3
|
|
100%
|
446.16V
|
+5%
|
424.8V
|
3.
|
33 KV-9%
|
|
|
|
|
3.1
|
|
0%
|
394V
|
-5%
|
414.7V
|
3.2
|
|
50%
|
378V
|
-5%
|
398.1V
|
3.3
|
|
100%
|
362.5V
|
-5%
|
381.5V
|
From the above
table, it can be observed that steady state 433V bus voltage is maintained for
the expected voltage variation on 33 KV side and various load conditions.
4.5.6 The class-III power supply should automatically
come on stream when the class-IV power supply fails due to any reason. All the
essential base loads like lighting, health and safety instruments, plant
communication equipment etc., should be energized within time duration of 30
–100 seconds. Power supply for all other bulk loads like exhaust and off-gas
fans should be made available within a time span commensurate with the health
and safety requirement.
4.5.7 Rating of the two DG sets shall be so chosen
that the entire class-III loads of the plant can be continuously fed even if
one of the sets is not available.
4.5.8 Bulk-oil
storage facility for DG Room shall be common for ROP, PREFRE & IP-1, which
shall be suitably located between PREFRE and IP-1 and shall be about 15m away
from any adjacent structure. Day tanks for ROP DG sets are to be near ROP
substation adjacent to the furnace oil storage bldg.
4.5.9
In most of the plant areas, 30-40% of the lights installed shall be
provided with class-III power supply whereas in control room, 50% of the lights
installed shall be provided with class-III power supply & rest from
class-II. Some of the plant facilities shall have special lighting provisions
such as 250 W HPSV/ 500 W halogen lamp fixtures for fuel pond lighting,
150/250W high pressure sodium vapour lamps in the dissolver cell, 250 W HPSV
for process cells, 35W/55 W SOX/ 18 W CFL for Hot cell & Blister (cubicles)
lighting Flame proof fixtures with ML lamps for inflammable material stores. All
the distribution boards have been provided with a 25% diversity factor.
4.5.10 The instrument power distribution
board (IPDB) providing control power supplies to various instruments in control room,
shall be fed with two feeders of Class II power. Each feeder shall be capable
of meeting the entire instrumentation load. Duplication of feeders is to
enhance the reliability and availability of power supply for the
instrumentation system.
4.5.11 Class-I DC power supply to critical
control relays, instruments & sub-station auxiliary loads shall be fed
continuously through DC switchboard receiving power normally from the ACVRs and
backed up with storage batteries.
4.5.12 Battery banks shall be adequately
designed to supply the entire class-I power requirement for a period of 30
minutes at high discharge rates without affecting the life of batteries.
4.5.13 In the event of non availability of
Class IV or Class III power supply to ACVRs, or during failure of ACVRs, the
batteries take over the function of feeding DC power to plant's critical loads
like switch gear controls, indications, communication system and also to the DC
`EXIT’ lighting along the evacuation routes in active areas.
4.5.14 The system design should ensure the
safety of plant equipment and that of the operating /maintenance personnel not
only during normal operation but also during emergency conditions like outbreak
of fire.
4.5.15 The design should be such that all
important process loads can be controlled from the main control room. Indication
of the availability of power supplies and ON/OFF status of major loads should
also be available at the control room.
4.5.16 The layout of the power distribution
centers should be such as to avoid lengthy cabling so that voltage drops can be
minimized with consequent improved performance of plant equipment.
4.5.17 All major load centres should be
segregated from each other so that planned or non- planned power interruption
in one area does not affect the operation in other areas.
4.5.18 All electrical motors shall be
connected through DOL type starter but for E2 fan motors
which will have VVVF drives.
4.5.19 Design shall facilitate control of
all important process loads from main control room.
4.6 Safety
requirements
4.6.1 There should be total segregation of class-IV,
class-III and class-I power supply system.
4.6.2 D.G. rooms
shall be partitioned with 3 hour fire rating wall.
4.6.3 The design should facilitate frequent in-service
inspections and preventive maintenance for ensuring the uninterrupted
availability of power for plant.
4.6.4 Separate cable trenches shall be provided for
laying of power and control/ instrumentation cables.
4.6.5 Diverse cable routes shall be followed for
group-A and group-B cables of safety related systems.
4.6.6 The enhancement of electrical system’s safety
shall be maintained by using requisite quality materials and equipments.
4.6.7 Fire and Smoke detectors shall be provided in
cable allies and at the top of electrical cables and panels (details given in
Fire protection system DBR of ROP).
4.7 Site specific requirements
The system design shall be suitable for the
following ambient conditions and the site environment:
1
1.1
|
Elevation
above sea level
Distance
from sea coast
|
Near
sea level
About
1500 mtrs.
|
2
|
Ambient
air temperature
|
|
2.1
|
Maximum
|
45°C
|
2.2
|
Average
daily (max.)
|
35°C
|
2.3
|
Design
temperature for electrical equipments
|
45°C
|
3
|
Relative
Humidity
|
|
3.1
|
Maximum
|
98%
|
3.2
|
Design
RH for electrical equipments
|
98%
|
4
|
Maximum
RH and temperature occurring simultaneously
|
80% and
40°C resp.
|
5
|
Air
Quality
|
Clean
|
6
|
Seismic
data
|
Zone 2
on seismic scale
|
7
|
Soil
resistivity
|
100
ohm-m
|
8
|
Available
off-site power source
|
2 nos.
of adequately rated 33 KV, 1500 MVA feeders
|
4.8 Standardization
of design
4.9 4.8.1 The system engineering should adopt
reliable, easy-to-maintain type of equipment so that maintenance work can be
carried out safely and quickly. The equipments/ components/ materials used
should be of tested and of proven performance, supplied by manufacturers of
established reputation.
4.8.2 The system components and the equipments shall
be of proven design and duly qualified for the application involved.
4.8.3 The equipment and the materials shall be so
standardized that stock of inventory for O&M can be minimized to the extent
possible.
4.10
Design changes/ improvements over
previous plants
Following changes and improvements are envisaged in
design of electrical systems as per ASPRC recommendations, various plants’s
feedbacks and site constraints.
4.9.1 Dry type
Cast Resin/ resin impregnated power and Distribution transformers shall be used
in place of oil filled transformers for enhancement of system safety and the
reliability.
4.9.2 It is
proposed to provide a remote control centre through SCADA system for substations,
MCCs/ PCCs etc. preferably to be extended to the main control room for better
co-ordination amongst the operating staff and also to reduce manpower. State of
the art protective devices viz. Numerical relays shall be used for sub-station
equipments. Qualification verification and reliability analysis have been
carried out for the numerical relays for its suitability under Indian
conditions.
4.9.3 Variable Voltage Variable Frequency (VVVF)
drives shall be provided for all the ACVE system, Utilities & Services
system equipments and also for some major motor pump sets for speed/flow
control and the resultant energy conservation.
4.9.4 A PLC based Emergency Transfer system is
envisaged for automatic sequential starting of all class III loads during power
outage of Mains power supply.
4.9.5 Lighting transformer shall be provided for
isolation purpose for high block as well as sub-station & low block. Power
supply for lighting can be made available from the dedicated 415/415 V, 3 phase
AN type isolating transformer of adequate rating.
4.9.6 A separate common utility control room shall be
provided for the remote control of all the utilities and services of the plant.
4.9.7 Process cells shall be equipped with ‘SON’
lights through shielding plugs (with drawable type). ‘Gold plated’ 230V plug
receptacles with local switch shall be provided in cells for maintenance. The
shielding plug light shall be designed to withstand total cumulative dose of
100 MR.
4.9.8 16 kA SPN MCBs shall be provided for lighting
& plug-circuits with separate neutral for each circuit . Also, HFFR wires
shall be used for building electrification.
4.9.9 All major load centers shall have independent
Motor Control Centres (MCC) for the group-A and group-B motors in equal number,
for enhancement of reliability and redundancy.
4.9.10 Power Factor Improvement (PFI) capacitor banks
are planned in ROP sub-station, distributed on both the buses of 415 V Class IV
switchgear, and also at the major load centres.
4.9.11 All the important emergency power systems
including DG sets, DG control panels &
auxiliaries, Class III switchgears, redundant Motor Control Centres, UPS
systems, DC battery Banks, ACVRs etc. shall be physically separated to avoid
common mode failures.
4.9.12 Stainless Steel fixtures shall be used for
areas likely to have acid fumes such as Tank Space, Make-up Area etc.
4.9.13 XLPE insulated, FRLS inner and outer sheathed
cables shall be used in 415 V AC and 110 V/ 48 V DC systems.
4.9.14 HFFR wires shall be used for the building
electrification of low and high block building.
4.9.15 Armored cables are to be used for all the
outdoor applications and in-door applications, as applicable. All single core
AC circuit cables will have aluminum armoring, otherwise round galvanized steel
wire armoring shall be used for other systems’ cables.
4.9.16 Energy conservation in lighting shall be
achieved through the use of CFLs, low loss/ electronic ballasts/ inverters. Also,
‘PID’ control shall be used for 50% ‘Normal’ lights in sampling gallery/ isolating
corridor for energy saving.
4.9.17 Suitable Tie- lines are provided for 415V ROP
class-IV switchgear with the class-IV switchgear of PREFRE substation to
facilitate sharing of power between ROP & PREFRE, during system failures under administrative
controls.
4.10.1 Necessary
interlocking between breakers and auto load transfer facility shall be
provided.
4.10.2 All the components and panels of
the emergency control room (located in high block building of R.O.P.)
including class-II UPS systems, shall be seismically qualified for SSE (Safe
Shutdown Earthquake) level of earthquake as per IEEE-344 standards. Electrical system shall
otherwise conform to IS-1893 for seismic requirements.
4.10.3 In view of low smoke densities and
high radiation resistance, Chloro Sulphonated
polyethylene (CSPE) has been provided as
sheathing material for power and control cables installed
in process cells and other highly
radioactive areas. Flame Retardant Low Smoke Polly Vinyl
Chloride (FRLS-PVC) sheathed cables have
been used in control room and other critical areas.
4.10.4 Earth mat network having stranded
copper conductor with spacing of 11 meters between the
parallel conductors forming grid has been
provided for grounding system of the plant.
4.10.5 All the structures under ROP
Project, including the stack, have been
covered under the
lightning protection system adopted for the
plant.
4.10.6 All the
major load centers shall be segregated from each other so that planned or
non-planned
5.0 METHODS & TECHNIQUES:
5.1 Two 33
kV(E), 400 sq. mm. 3 core under ground
cable feeders from MSEB/ TAPS-1 & 2
switchyard, taken from two different bus sections shall feed 33 KV switchgears of ROP sub-station for
distribution of 33 KV power supply for PREFRE substation, ROP substation
and proposed UNCF substation.
5.2 Substation shall be
provided with ventilation air through supply air duct. Sub station control room shall have split air conditioner or
split chilled water- fan coil unit sets for ensuring smooth functioning of sophisticated softwares and
hardwares.
5.3 Transformers
room shall be provided with roof at top at about 5.5 m height. Transformer
rooms
shall be
partitioned with each other.
5.4 The layout of the power distribution centres
should be such as to avoid lengthy cabling so that
voltage drops
can be minimized with consequent improved performance of plant equipment.
5.5 Monorails
with chain pulley blocks are required in electrical workshop, DG room, lift
rooms.
5.6 Installation of
electrical PCC/MCCs/PDBs,
Distribution panels and
control panels shall be
made in separate
and readily accessible areas, rooms/ enclosures attached to the plant areas such as tank space, access
galleries, off gas rooms, FHA, labs, so
as to avoid their exposure
to the corrosive &
radio-active environment.
5.7 All electrical motors shall be connected through
DOL type starter but for E2 fan motors, which
will have VVVF drives. Running hour meter shall be
provided for all the utility & services system motors.
5.8 There should be provision of fire and smoke
sensors in cable allies and top of electrical cables/
panels.
5.9 Fire breaks/
barriers shall be provided wherever the cable crosses the floor/ ceiling.
5.10 There should be sealing on hume pipe sleeves
meant for cable entry(s) into the plant
buildings
(as anti-flood measures).
5.11 Separate cable routes/ trays shall be provided
for laying of power and control/ instrumentation
cables.
6.0
SYSTEM
CONFIGURATION
6.1
CLASS-IV POWER SUPPLY SYSTEM
Reliable ‘mains’
class-IV power supply is required for normal operation and maintenance of the
plant.
Two 33 kV
under ground cable feeders from
MSEB/ TAPS-1 & 2 switchyard,, taken from two different bus sections shall
feed the ROP sub-station through 33 kV
switchgear to be housed in new indoor substation as per single line diagram/ drawing no.1. The ROP sub-station will provide 415 V, 3 phase, 4 wire A.C. power
supply to all the plant loads. These two
33 KV HT incoming feeders to ROP HT switchgear will be used for ROP site,
ensuring practically two independent sources of power supply to the plant.
The following equipments are planned in an indoor ROP
sub-station for the class IV power system :
(1) 33 kV Vacuum circuit breakers .
(2) SCADA based switchgear system for 33 kV and
415 Volt power system.
(3) 33/ 0.433 kV, 2.5 MVA Dry type
transformers.
6.2
CLASS-III POWER SYSTEM
Some of the
equipment of the plant such as the exhaust & off-gas fans; part of the
lighting in the active areas of the plant; installed health physics instruments
and some of the vital in-process control/measurement instruments have to be
available all the time on considerations of plant and personnel safety. For
this purpose, class-III power system has been provided.
‘Emergency’ DG sets backed up class-III power supply
is required for operation of such safety
related and important loads of plant during outage of
class-IV power supply.
Two numbers of diesel generator sets of approximately 1010 kVA capacity each, shall
provide 415 V, 50 HZ grounded AC power supply
to safety related loads during
class-IV power failure/outage conditions
through a network independent of the class-IV power distribution. The
total emergency power requirement of the ROP Project/AWTF is estimated at about
850 kVA.
The class-IV and class-III load particulars are given
in Table-II & III respectively.
6.3 CLASS-II
POWER SYSTEM
Two independent 230 V, 50 kVA, AC single phase
class-II uninterruptible power supply (UPS) set shall be provided for critical
control systems viz. SCADA system, Public Address System, criticality monitors,
control instruments, turnstile gates etc.
Two class-III power feeders shall be dedicated for the UPS system for
continuous availability of power supply to these critical systems. Class-II
load list is tabulated in Table-IV.
6.4 CLASS-I POWER SYSTEM
Critical control instruments and auxiliary loads of
the plant need class-I DC power supply. These will be fed continuously with DC
power through the ACVR backed up by storage batteries.
The exit lighting provided in the main control
room/other control centres and at all the escape/exit routes of the plant shall
be connected to this power system. During emergency situations and class-IV
power failure conditions, these lights come on automatically before the Diesel
Emergency Power system takes over. This power system is categorized as class-I.
Two battery banks, each of 110 V (nominal), 425 AH, 56 Cell YKP 35 plante type,
shall provide Class-I, 110 V DC power supply to DC loads, in the event of
non-availability of Class IV or Class III power supply on DC switchboard /ACVR
terminals. Battery banks of 24V DC shall be provided for DG controls. Class-I
DC load list is tabulated in Table-V.
7.0 SYSTEM DESCRIPTION
7.1 INCOMING POWER SUPPLY TO ROP SUBSTATION
Two 33 kV
overhead MSEB lines are terminated in MSEB/NPC tapyard behind PREFRE complex. 2
nos. underground 400 sq. mm 3 core XLPE armoured cables are laid from the new
switch yard to ROP HT switchgear. These two 33 KV HT incoming feeders to ROP HT
switchgear will be used for ROP site, ensuring
practically two independent sources of power supply to the plant.
These two 33 kV feeder lines from MSEB/NPC switchyard,
taken from two different bus sections shall feed the ROP sub-station through 33 kV switchgear to be housed in new
indoor substation as per single line diagram/ drawing no. 1. The ROP
sub-station will provide 415 V, 3 phase, 4 wire ac
power supply to all the plant loads. Thus the plant
shall have practically two independent sources of power assuring a reliable
power supply.
7.2 SUB-STATION
The existing 33 kV outdoor switchyard provided in
PREFRE plant for receiving and distributing ‘Mains Class–IV’ power supply for
plant’s regular O&M needs, has 2 Bulk-oil circuit breaker and gang-operated
switches with drop-out type fuses for protecting the complete Mains power
system, which were installed during early 70’s. These designs are outdated,
unreliable and inadequate to provide protections as per safety codes. Also,
some of these devices have become unsafe and inoperable due to heavy corrosion,
wear & tear under salt-laden atmosphere. Due to above reasons and because
of their inadequate capacity to meet the enhanced load requirements of PREFRE
plant and ROP project, it has been decided to renovate the complete power
system of the plant by providing the following equipments of state-of-art
technologies in an indoor ROP sub-station :
(1) 33 kV Vacuum circuit breaker.
(2) SCADA based switchgear system for 33 kV
and 415 Volt power system.
(4) 33/ 0.433 kV, 2.5 MVA Dry type
transformers.
(5) 2 nos., 1010 KVA, 3 phase, 433V D.G. sets.
(6) A static, high efficiency class-II UPS
system for plant’s critical requirements.
(7) Class-I power system for managing total
blackout condition in the plant.
The layout of the sub-station shall be such that the
load centres are close to the sub-stations thereby avoiding lengthy cabling.
Consequently, voltage drops are expected to be minimal with improved equipment
performance. The sub-station is indoor, non-exposed type. XLPE cables shall be
laid through accessible cable trenches for interconnection of transformers and
HT switchgears
ROP sub-station
building is planned behind PREFRE Low Block building by demolishing the
existing outdoor 33 kV PREFRE switchyard. The low block building accommodates
most of the utilities/services systems of PREFRE and ROP. This substation will
thus feed major electrical loads like V2- fans, refrigeration compressors
etc. HT switch gears and the storage
batteries for the DC power supply shall also be located in this sub-station.
This sub-station shall also cater to the process loads and the exhaust
fans. The two diesel generators that
supply emergency power to the plant shall also be installed in this
sub-station.
7.2.1 SALIENT
FEATURES OF R.O.P. SUB-STATION
7.2.1.1
Physical separation of
class-IV, class-III, class-II and class-I power supply systems.
7.2.1.2 Risk of
fire hazards is avoided by using cast resin power transformers and vacuum
circuit breakers.
7.2.1.3 Physical
separation of class-III emergency bus
sections.
7.2.1.5
Separate
cable routings for class-IV, class-III, class-II and class-I power and control cables.
7.2.1.6 All cables have FRLS (Fire resistance low
smoke) inner and outer sheaths.
7.2.1.8 PLC
based auto sequential starting of
loads.
7.2.1.9
.Improvement of power factor by using APFC (Automatic power factor correction)
panels.
7.2.1.10
Substation control room shall have SCADA based data management and
control.
7.3 CLASS-IV
POWER SUPPLY SYSTEM
7.3.1 TRANSFORMERS (GENERAL FEATURES)
The power
transformers for ROP electrical system shall be of in-door, cast resin
encapsulated, epoxy impregnated, dry type and air cooled type. The transformers
shall have essential protective devices for safe and reliable operation.
Two number of transformers (33 kV/0.433 kV, 2500 kVA
rating) shall be installed in sub-station. The transformers can withstand the
maximum rated current at -2.5% tap on HV side and they can also withstand 110%
continuous overflowing. They shall be capable of withstanding 3 starts per hour
(under hot conditions) at DOL starting of highest rating motors with maximum
base load. Maximum noise level of the 2500 kVA transformer is 65 dB. The
neutral point of star connection can withstand highest over current. They are
equipped with winding temperature controllers. Core, windings, terminals, tap changers,
auxiliaries shall be designed for continuous and short time overload capacity.
It gives maintenance free operation. It has highest level of safety measures.
The transformers are class-H insulated cast resin system. Cast resin offers
high mechanical strength, improved earth tracking resistance, high dielectric,
moisture repellent and flame retardant qualities. The transformers shall have
‘Over current’, ‘Earth fault’, REF (Restricted Earth Fault) and winding
temperature protection using RTDs. Technical particulars of Dry type transformers
are listed in Table VI.
The transformer rooms shall be provided with roof at
the top. They are isolated from each other by the partitioning walls so that in
the event of fire, it’s spread can be avoided. Provision of exhaust fans may
also be available for better ventilation of the room.
No comments:
Post a Comment